Unless it is otherwise structurally supported, all track shall
be supported by material which will --
103(a) Transmit and distribute the load of the track and
railroad rolling equipment to the subgrade;
103(b) Restrain the track laterally, longitudinally, and
vertically under dynamic loads imposed by railroad rolling equipment and thermal
stresses imposed by the rails;
Guidance: Ballast
may consist of crushed slag, crushed stone, screened gravel, pit-run gravel,
chat, cinders, scoria, pumice, sand, mine waste, or other native material, and
is an integral part of the track structure. Ballast, regardless of the material,
must satisfy the requirements stated in the TSS.
103(c) Provide adequate drainage for the track; and
103(d) Maintain proper track crosslevel, surface, and alinement.
Guidance:
Inspectors
should consider the overall condition of a track when citing fouled ballast.
Because ballast conditions can be subjective in nature, inspectors should also
look to other indicators, such as a geometry condition. For example, a fouled
ballast violation might be appropriate if the track has poor drainage and there
is a geometry condition or a series of fouled ballast locations with geometry
conditions.
The term "geometry condition" used here and elsewhere in this
manual means a track surface, gage, or alinement irregularity that does not
exceed the allowable threshold for the designated track class. It exists due to
the reduced or non-existent capability of one or more track structural
components to hold the track to its preferred geometric position.
109(a) Crossties shall be made of a material to which rail can
be securely fastened.
109(b) Each 39-foot segment of track shall have
at a minimum-
(1) A sufficient number of crossties which in combination
provide effective support that will -
(i) Hold gage within the limits prescribed in
§213.53(b);
(ii) Maintain surface within the limits prescribed in
§213.63;
and
(iii) Maintain alinement within the limits prescribed in
§213.55.
(2) The minimum number and type of crossties specified in paragraph (b)(4) of
this section and described in paragraph (c) or (d), as applicable, of this
section effectively distributed to support the entire segment;
(3) At least one non-defective crosstie of the type specified in paragraphs
(c) and (d) of this section that is located at a joint location as specified in
paragraph (e) of this section; and
(4) The minimum number of crossties as indicated in the following table.
Guidance: The
TSS determines the adequacy of crosstie support by including its functional
requirements to maintain track geometry within the limits specified in Subpart
C. The failure of the crossties to meet any of the three above criteria
constitutes a deviation from the TSS.
Effective distribution has not been defined, but must not be interpreted by
the inspector as synonymous with equally spaced. The language is intended to
address situations where all of the nondefective or defective ties exist in a
group at a short area of the 39-foot segment of track in question. Evidence that
crossties are not effectively distributed includes, primarily, indications of an
actual deviation or a geometry condition.
No criterion exists for the maximum distance between nondefective ties, and
this measurement should not be used to describe a tie defect. If such a
description is appropriate, it should be in terms of the number of consecutive
defective ties in a group.
When citing 213 defect code 0109B2 (Crossties not effectively distributed to
support a 39-foot segment of track), the inspector must show evidence of one or
more of the geometry conditions cited in § 213.109(b)(1). Several factors may
be documented if the defect is being cited. These factors include, but are not
limited to:
• Geometry conditions.
• Class of track.
• Curvature.
• Traffic density (annual tonnage).
• Rail weight and condition.
• Condition of other components of the track.
When determining compliance with this section, the inspector must determine
that crossties meet the requirements of effectiveness as defined above and make
geometry measurements to verify that each 39-foot segment of track has:
• A sufficient number of effective ties to maintain geometry.
• The required number of nondefective ties for the track class as described
in paragraph
213.109(b)(4).
• The proper placement of nondefective ties as described in paragraph
213.109(b)(4) and positioned as required in paragraph (e) to support joints.
The majority of crossties throughout the nation are made from wood. However,
there are varieties of alternate designed crossties made from materials such as
composites, steel, and concrete. These types of crossties are becoming more
common throughout the industry. Because of the increased use of these alternate
design crossties and their associated resilient type rails fasteners, inspectors
should more rigorously consider the rail/crosstie interface. Also, see § 213.127, Rail fastenings.
109(c) Crossties, other than concrete, counted to satisfy the requirements set
forth in paragraph (b)(4) of this section shall not be—
(1) Broken through;
(2) Split or otherwise impaired to the extent the crossties will
allow the ballast to work through, or will not hold spikes or rail fasteners;
(3) So deteriorated that the tie plate or base of rail can move
laterally more than ½ inch relative to the crossties; or
(4) Cut by the tie plate through more than 40 percent of a ties’
thickness.
Guidance:
Paragraph
(c) mainly applies to wooden ties, although it does not explicitly exclude
composite and steel ties.
When a crosstie exhibits any one or more of the conditions described in the
four criteria for evaluation [§ 213.109(c)1–4] it may be considered
non-effective itself, although that determination may not always result in a
defective condition that can be recorded under 213 Defect Codes 0109A, 0109B2,
or 0109B3.
If track geometry measurements fail to meet the requirements of Subpart C,
and there are an insufficient number of effective crossties, both geometry and
crossties could be cited as defects. If geometry measurements exceed the
allowable tolerance, but a determination cannot be made that crossties are the
cause, it is appropriate to cite only the defective geometry.
FRA inspectors may use a PTLF described in § 213.110 for the purposes of
measuring loaded gage to determine effective distribution of crossties. Refer to
Appendix D–PTLF, instructions for non-GRMS territory under § 213.53.
109(d) Concrete crossties
counted to satisfy the requirements set forth in paragraph (b)(4) of this
section shall not be--
(1) Broken through or deteriorated to the extent that
prestressing material is visible;
(2) Deteriorated or broken off in the vicinity of the shoulder
or insert so that the fastener assembly
can either pull out or move laterally more than ⅜ inch relative to the
crosstie;
(3) Deteriorated such that the base of either rail can move
laterally more than ⅜ inch relative to the
crosstie on curves of 2 degrees or greater; or can move laterally more than ½
inch relative to the crosstie on tangent track or curves of less than 2 degrees;
(4) Deteriorated or abraded at any point under the rail seat to
a depth of ½ inch or more;
(5) Deteriorated such that the crosstie’s fastening or
anchoring system, including rail anchors (see § 213.127(b)), is unable to
maintain longitudinal rail restraint, or maintain rail hold down, or maintain
gage due to insufficient fastener toeload; or
(6) Configured with less than two fasteners on the same rail
except as provided in § 213.127(c).
Guidance:
Crossties
are evaluated individually by the definitional and functional criteria set forth
in the regulations. Crosstie "effectiveness" is naturally subjective
and requires good judgment in the application and interpretation of this
standard. The soundness and durability of a crosstie is demonstrated when a
39-foot track segment maintains safe track geometry and structurally supports
the imposed wheel loads with minimal deviation. Key to the track segment
lateral, longitudinal, and vertical support is a strong track modulus, which is
a measure of the vertical stiffness of the rail foundation. Continuous superior
superstructure (including rails, crossties, fasteners, etc.) and high-quality
ballast characteristics that transmit both dynamic and thermal loads to the
subgrade are also important. Proper drainage that is free from the presence of
excess moisture is an apparent and crucial factor in providing added structural
support.
Section 213.109 contains specific performance requirements for FRA Classes
1 through 5 track that address the unique characteristics of fastener
reliability, concrete crossties, and roadbed stability. Inspectors should be
aware of the three modes of concrete crosstie failure: support, stability, and
electrical isolation. The compressive strength of concrete and the amount of
prestress in its section composition provide the strength and stiffness
necessary to support expected wheel loads. There is a balance between excessive
stiffness that can lead to higher stresses at the bottom of the crosstie and at
the rail seat.
Conversely, a loss of stiffness, caused by ever increasing axle loading,
can lead to excessive rail deflections and damage to the ballast and subgrade.
Inspectors should be aware that failure modes are not isolated to crosstie
defects. Combinations of compliant but irregular track and rail geometry, poor
drainage, insufficient ballast depth and subgrade soil conditions may contribute
to failure or root causal factors.
Paragraph (d) delineates the requirements related to concrete crossties.
Modern concrete crossties are designed to accept the stresses imposed by
irregular rail head geometry and loss, excessive wheel loading caused by wheel
irregularities (out of round), excessive unbalance speed, and track geometry
defects. Section 213.109 considers the worst combinations of conditions, which
can cause excessive impact and eccentric loading stresses that would increase
failure rates and other measures concerning loss of toeload, longitudinal and
lateral restraint, in addition to improper rail cant.
Paragraph (d) (1) states that as with non-concrete crossties, concrete
crossties counted to fulfill the requirements of paragraph (b)(4) must not be
broken through or deteriorated to the extent that prestressing material is
visible.
Crossties must not be so deteriorated that the prestressing material has
visibly separated from, or visibly lost bond with, the concrete, resulting
either in the crosstie’s partial break-up, or in cracks that expose
prestressing material due to spalls or chips, or in significant broken-out areas
exposing prestressed material. Currently, metal reinforcing bars are used as the
prestressing material in concrete crossties. FRA uses the term "prestressing
material" in lieu of "metal reinforcing bars" to allow for future
technological advances.
There is a distinction between the phrases "broken through" and
"deteriorated to the extent that prestressing material is visible."
Concrete crossties are manufactured in two basic designs: twin-block and
mono-block. Twin-block crossties are designed with two sections of
concrete
connected by exposed metal rods. A mono-block crosstie is similar in dimension
to a timber or wood crosstie and contains prestress metal strands embedded into
the concrete. The prestressing material in the concrete is observed at the ends
of the crosstie for proper tension position. Prestressed reinforced concrete
crossties are made by stressing the reinforcing material in a mold, then pouring
cement concrete over the reinforcing material in the mold. After the concrete
cures, the tension on the reinforcing material is released, and the ends of the
reinforcing material are trimmed, if appropriate for the use. The prestressing
material remains in tension against the concrete, which is very strong in
compression. This allows the prestressed concrete to withstand both compressive
and tensile loads. If the concrete spalls, or if the prestressing material is
otherwise allowed to come out of contact with the concrete, then the
prestressing material is no longer in tension. A concrete crosstie’s flexural
strength and stiffness is lost when the prestress force is reduced through
corrosion, concrete deterioration, or poor bond with the concrete due to
improper manufacturing. The prestressing material may corrode if insufficient
concrete cover or concrete cracking allows the intrusion of moisture and oxygen.
When this happens, the once prestressed concrete crosstie can no longer
withstand tensile loads, and it will fail very rapidly in service.
Prestressing material is often exposed in a concrete
crosstie as a crack, but it can also be exposed on the side of the tie. When
prestressing material becomes exposed on the side of a crosstie, the
prestressing material is no longer in tension, the prestressed concrete can no
longer withstand the tensile loads, and therefore a concrete crosstie can
structurally fail. This does not apply to reinforcing material left visible at
the end of the crosstie during the manufacturing process.
The compressive strength of the concrete material and
the amount of prestress applied in the manufacturing process provide the
strength and stiffness necessary to adequately support and distribute wheel
loads to the subgrade. The prestressing material encased in concrete hold the
crosstie together and provides tensile strength. However, significant cracking
or discernible deterioration exposure of the reinforcing strands to water and
oxygen produces loss of the prestress force through corrosion, concrete
deterioration, and poor bonding. Loss of the prestress force renders the
crosstie susceptible to structural failure and as a consequence, stability
failure relating to track geometry noncompliance.
Crossties transversely broken between the rail seats
and showing signs of further deterioration (loss of tension in prestressing
material—upper and lower levels of exposure to metal strands) constitute
failure. This means that there cannot be a complete separation of the concrete
material making up the crosstie. Crossties must not be so deteriorated that the
prestressing material has visibly separated from, or visibly lost bond with, the
concrete, resulting either in the crosstie’s partial break-up, or in cracks
that expose prestressing material due to spalls or chips, or in significant
broken-out areas exposing prestressed material.
Crosstie failure is exhibited in three distinct ways:
stress induced (breaks, cracks); mechanical (abrasion); or chemical
decomposition. These conditions in small or large degrees compromise the
crosstie’s ability to maintain proper gage, alignment, and track surface.
Walking inspections would demonstrate clearly visible spalls, chips, cracks, and
similar breaks. However, the compression of prestressed concrete crossties may
close cracks as they occur, making them difficult to observe. Even such closed
cracks probably weaken the crossties.
Breaks or cracks are divided
into three general conditions: longitudinal cracks, center cracks, and rail seat
cracks. Longitudinal cracks are horizontal through the crosstie and extend
parallel to its length. They are initiated by high impacts on one or both sides
of the rail bearing inserts. Crosstie center cracks are vertical cracks
extending transversely (across) the crosstie. These cracks are unusual and are
the result of high negative bending movement (usually center bound), originating
at the crosstie top and extend to the bottom. Generally, the condition is
progressive, and adjacent crossties may be affected. Rail seat cracks are
vertical cracks that are not easily visible. They usually extend from the bottom
of the crosstie on one or both sides of the crosstie and are often hard to
detect. It is possible for a crosstie to be broken through, but, due to the
location of the break, the prestressing material may not be visible. Crosstie
strength, generally, does not fail unless the crack extends through the top
layer of the prestressing material. Once the crack extends beyond the top layer,
there is usually a loss of prestressing material and concrete bond strength.
Paragraph
(d) (2) makes clear
that crossties counted to fulfill the requirements of paragraph (b)(4) of this
section must not be deteriorated or broken off in the vicinity of the shoulder
or insert so that the fastener assembly can either pull out or move laterally
more than three-eighths inch relative to the crosstie, as these conditions
weaken rail fastener integrity.
Paragraph (d)
(3) provides that
a crosstie counted to fulfill the requirements of (b)(4) must not be
deteriorated such that the base of either rail can move laterally more than
three-eighths inch relative to the crosstie on curves of 2 degrees or greater;
or can move laterally more than one-half inch relative to the crosstie on
tangent track or curves of less than 2 degrees. This section allows for a
combination rail movement, inward and outward, up to the dimensions specified,
but not separately for each rail. The rail and fastener assembly work as a
system capable of providing electrical insulation, adequate resistance to
lateral displacement, undesired gage widening, rail canting, rail rollover, and
abrasive or excessive compressive stresses. In accordance with policy and
procedures, inspectors are encouraged to use the assigned portable track loading
fixture (PTLF) in assessing the amount of lateral rail movement, wherever
applicable.
Paragraph
(d) (4) requires that
crossties counted to fulfill the requirements of paragraph (b)(4) of this
section must not be deteriorated or abraded at any point under the rail seat to
a depth of one-half inch or more. The measurement of one-half inch includes
depth from the loss of rail pad material. The importance of having pad material
in place with sufficient hysteresis (i.e., resilience (elasticity) to dampen
high impact loading and recover) is paramount to control rail seat cracks caused
by rail surface defects, wheel flats, or out of round wheels. Additionally,
concrete crossties must be capable of providing adequate rail longitudinal
restraint from excessive rail creepage or thermally induced forces or stress.
"Rail creepage" is the tractive effort or pulling force exerted by a
locomotive or car wheels, and "thermally induced forces or stress" is
the longitudinal expansion and contraction of the rail, creating either
compressive or tensile forces as the rail temperature increases or decreases,
respectively. The loss of pad material causes a loss of toeload force, which may
decrease longitudinal restraint. See the following figure. Note: inward or
outward rail cant angle conventions are interchangeable among geometry
measurement systems. FRA geometry cars record inward cant as positive, and
outward cant as negative.
Paragraph
(d) (5) requires that crossties counted to fulfill the
requirements of paragraph (b)(4) of this section must not be deteriorated such
that the crosstie’s fastening or anchoring system including rail anchors is
unable to maintain longitudinal rail restraint, maintain rail hold down, or
maintain gage, due to insufficient fastener toeload. Inspectors evaluate
crossties individually by "definitional and functional" criteria. A
compliant crosstie is demonstrated when a 39-foot track segment maintains safe
track geometry and structurally supports the imposed wheel loads. In addition to
ballast, anchors bear against the sides of crossties to control longitudinal
rail movement, and certain types of fasteners also act to control rail movement
by exerting a downward clamping force (toeload) on the upper rail base. Part of
the complexity of crosstie assessment is the fastener component. Both crossties
and fasteners act as a system to deliver the expected performance effect. A
noncompliant crosstie and defective fastener assembly improperly maintains the
rail position and support in the rail seat and contributes to excessive lateral
gage widening (rail cant-rail rollover), and longitudinal rail movement because
of loss of toeload.
Fastener assemblies or anchoring systems allow a certain amount of rail
movement through the crosstie to effectively relieve rail creepage (tractive and
thermal force build-up). However, because of the unrestrained buildup caused by
rail creep, the longitudinal expansion and contraction of the rail creates
either compressive or tensile forces, respectively. When longitudinal rail
movement is ‘uncontrolled,’ it may disturb the track structure, causing
misalignment (compression) or pull-apart (tensile) conditions to catastrophic
failure. Specific longitudinal performance metrics would be undesirable and
restrict certain fastener assembly designs and capabilities to control
longitudinal rail movement. Therefore, inspectors must use good judgment in
determining fastener assembly and crosstie effectiveness.
Paragraph (b)(6) makes clear that crossties counted to fulfill the
requirements of paragraph (b)(4) of this section must not be configured with
less than two fasteners on the same rail, except as provided in amended § 213.127(c), which includes requirements specific to fasteners used in
conjunction with concrete crossties. As with nonconcrete ties, one of the safety
requirements of an effective concrete tie is its ability to hold fasteners.
109(e) Class 1 and 2 track shall have one crosstie whose centerline is within 24
inches of each rail joint (end) location. Class 3, 4, and 5 track shall have
either one crosstie whose centerline is within 18 inches of each rail joint
location or two crossties whose centerlines are within 24 inches either side of
each rail joint location. The relative position of these crossties is described
in the following three diagrams:
(1) Each rail joint in Class 1 and 2 track shall be supported by at least one
crosstie specified in paragraphs (c) and (d) of this section whose centerline is
within 48 inches as shown in Figure 1.
(2) Each rail joint in Class 3, 4, and 5 track shall be supported by either
at least one crosstie specified in paragraphs (c) and (d) of this section whose
centerline is within 36 inches as shown in Figure 2, or:
(3) Two crossties, one on each side of the rail joint, whose centerlines are
within 24 inches of the rail joint location as shown in Figure 3.
Guidance:
A
nondefective joint tie must be found within the prescribed distance of the
centerline of the joint measured at the rail end. In Classes 3 through 5, joint
tie placement can be satisfied by either a one tie configuration, or by a
two-tie configuration.
For clarity of measurement and
description:
1. Where a short piece of rail
only inches in length is inserted between the rail ends and incorporated into
the joint bar assembly, measure from the bar centerline. Also see § 213.121(d),
Rail Joints.
2. Where nonsymmetrical bars
exist, (e.g., five-hole heel block bars, five-hole compromise bars) measure from
the design point where rail ends normally abut.
109(f) For track constructed without crossties, such as slab track, track
connected directly to bridge structural components, track over servicing pits,
etc., the track structure shall meet the requirements of paragraph (b)(1) of
this section.
Guidance:
This
paragraph addresses track constructed without crossties or bridge timbers, such
as concrete-slab track, in which running rails are secured through fixation to
another structural member.
In general, discrepancies may
arise in evaluation of crosstie conditions, if decisions are based only on an
inspector’s maintenance experience, which varies widely among the inspectors.
Inspectors should evaluate tie condition solely on the basis of the definitions
provided in this section. Each crosstie must be evaluated individually by these
criteria. As with all provisions of the TSS, the inspector must use judgment and
discretion in the application of the crosstie standards. They should be used to
describe conditions that constitute a risk to the safe operation of trains, and
should not be applied in doubtful cases.
Gage rods are not an effective
substitute for a proper crosstie and rail-fastening system. Gage rods can be
subject to sudden failure, they provide no vertical rail support, and they
provide no resistance to rail roll-over forces. However, gage rods may be
installed when they are used as a secondary means of support for maintaining
gage. Where gage rods are used and it is obvious that the condition of the
crosstie and fastening system in the immediate vicinity is incapable of
maintaining adequate gage, then the inspector should consider citing a crosstie
or fastener defect.
Certain crossties may not be able
to hold spikes or rail fasteners in their present condition. In these cases, it
may be possible to bring the crossties into compliance by either plugging and
re-spiking, or adding additional rail-holding or plate-holding spikes, or both.
Where conditions are closer to a
rail-fastener issue (e.g., sound ties in track are not fastened to the rail),
inspectors should refer to the guidance under § 213.127.
110(a) A track owner may elect to implement a Gage Restraint
Measurement System (GRMS), supplemented by the use of a Portable Track Loading
Fixture (PTLF), to determine compliance with the crosstie and fastener
requirements specified in § 213.109 and
§ 213.127 provided that--
(1) The track owner notifies the appropriate FRA Regional office
at least 30 days prior to the designation of any line segment on which GRMS
technology will be implemented; and
(2) The track owner notifies the appropriate FRA Regional office
at least 10 days prior to the removal of any line segment from GRMS designation.
Guidance:
This paragraph provides for the implementation of a GRMS, supplemented by the
use of a PTLF, to determine compliance with the crosstie and rail fastener
requirements specified in §§ 213.109 and 213.127. Track owners electing to
implement this technology must provide the appropriate FRA regional office with
notification that specifically identifies the line segments where GRMS will be
used. The appropriate FRA office is the headquarters location for the FRA region
in which the GRMS designated line segment is located.Track and Rail and
Infrastructure Integrity Compliance Manual Volume II, Chapter 1 – January 2014
2.1.61
The notification must be provided
to FRA at least 30 days prior to the designation of any line segment which will
be subject to the requirements of this section. Even though the notification
requirement is satisfied, and the GRMS vehicle is determined to meet the minimum
design requirements, the actual "triggering event," which places the
line segment under the GRMS requirements, is the initial track survey with the
GRMS vehicle.
Track owners must also provide
FRA with at least 10 days notice prior to the removal of a line segment from
GRMS designation. This requirement provides FRA with advance notice of the
criteria change for the inspection of crossties and fasteners, and places some
control over the random removal of line segments from GRMS designation.
110(b) Initial notification under paragraph (a)(1)of this
section shall include--
(1) Identification of the line segment(s) by timetable
designation, milepost limits, class of track, or other identifying criteria; and
(2) The most recent record of million gross tons of traffic per
year over the identified segment(s).
Guidance:
This
paragraph specifies what information track owners should include in their
notifications to FRA about line segments designated for GRMS inspection. The
information must include, at a minimum, the segment's timetable designation,
milepost limits, track class, million gross tons of traffic per year, and any
other identifying characteristics of the segment.
For reasons of safety, GRMS vehicles have their split-axle in the retracted
position when testing through special trackwork such as turnouts at grade
rail-to-rail crossings (diamond), expansion joints, lift rail assemblies, etc.
Where certain trackage within is not part of the designation, notifications
should identify what and where these locations are and what distance approaching
and leaving these locations are also excluded from GRMS designation. Locations
excluded from GRMS designation will be subject to the requirements of §§
213.109 and 213.127.
110(c) (1) The track owner shall also provide to FRA sufficient technical data to
establish compliance with the following minimum design requirements of a GRMS
vehicle:
(2) Gage restraint shall be measured between the heads of rail—
(i) At an interval not exceeding 16 inches;
(ii) Under an applied vertical load of no less than 10 kips per rail; and
(iii) Under an applied lateral load that provides for a lateral/vertical load
ratio of between 0.5 and 1.255, and a load severity
greater than 3 kips but less than 8 kips per rail.
5GRMS equipment using load combinations developing
L/V ratios that exceed 0.8 shall be operated with caution to protect against
the risk of wheel climb by the test wheelset.
Guidance: This
paragraph describes minimum design requirements for GRMS vehicles. Track owners
must submit to FRA sufficient technical data so that the agency can establish
whether the track owner is in compliance with these design requirements. This
paragraph requires that gage must be measured between the heads of the rail at
an interval not exceeding 16 inches. The paragraph provides for design
flexibility by establishing acceptable ranges for the lateral/vertical load
ratio and the resulting lateral load severity, both of which can
be satisfied by various load configurations, provided
that the applied vertical load is not less than 10 kips per rail.
The rule provides for design flexibility by
establishing acceptable ranges for various loading requirements. These ranges
are considered absolute, and loading configurations that fall outside of the
prescribed ranges will not be considered acceptable. Some loading configurations
may develop high lateral/vertical load ratios and therefore lubrication of the
gage face of the rail ahead of the split axle may be required to reduce the
coefficient of friction to prevent wheel climb. Footnote 5 to this section
cautions operations at L/V ratios exceeding 0.8 to protect against the risk of
wheel climb by the test wheelset. This footnote is identical to footnote 10,
which applies to § 213.333, Automated vehicle-based inspection systems, to
ensure conformity between this section and its subpart G counterpart.
5 GRMS equipment using load
combinations developing L/V ratios that exceed 0.8 shall be operated with
caution to protect against the risk of wheel climb by the test wheelset.
S = Load severity, defined as the lateral load applied to the
fastener system (kips).
L = Actual lateral load applied (kips).
c = Coefficient of friction between rail/tie, which is
assigned a nominal value of 0.4.
V = Actual vertical load applied (kips), or static vertical
wheel load if vertical load is not measured.
Guidance: This
paragraph prescribes a formula for the calculation of "load
severity" required by 110(c)(2) iii. The coefficient of friction at
rail/tie interface can change the load severity level when the applied actual
lateral and vertical loads are given. However, it is impractical to determine
the actual coefficients of friction, which vary from place to place in the
GRMS territory. A nominal value of 0.4 can always be used.
110(e) The measured gage values shall be converted to a Projected Loaded Gage 24
(PLG24) as follows—
PLG 24 = UTG + A × (LTG−UTG)
Where—
UTG = Unloaded track gage measured by the GRMS vehicle at a
point no less than 10 feet from any lateral or vertical load application.
LTG = Loaded track gage measured by the GRMS vehicle at a
point no more than 12 inches from the lateral load application point.
A = The extrapolation factor used to convert the measured
loaded gage to expected loaded gage under a 24-kip lateral load and a 33-kip
vertical load.
For all track—
Note: The A
factor shall not exceed a value of 3.184 under any valid loading
configuration.
L = Actual lateral load applied (kips).
V = Actual vertical load applied (kips), or static vertical
wheel load if vertical load is not measured.
Guidance:
This
paragraphs prescribes the formula for the calculation of the projected loaded
gage 24 (PLG 24). The formula provides a method to normalize the PLG
regardless actual lateral load loads applied by different GRMS systems.
Accurate measurements of unloaded gage, GRMS loaded gage, and the lateral load
applied are of critical importance because these measurements are used in the
calculation of PLG 24 values which constitute a direct measure of track
strength.
To minimize the influence from adjacent loads, the unloaded track gage (UTG)
must be measured by the GRMS vehicle at a point no less than 10 feet from any
lateral or vertical load application and the loaded track gage (LPG) at a
point no more than 12 inches from the lateral load application point.
110(f) The measured gage value
shall be converted to a Gage Widening Ratio (GWR) as follows
Guidance:
This
paragraph prescribes the formula for the calculation of the gage widening
projection (GWP). The GWP is intended to compensate for the weight of the
testing vehicle. Use of the GWP is supported by research results documented in
the report titled "Development of Gage Widening Projection Parameter for
the Deployable Gage Restraint Measurement System" (DOT/FRA/ORD-06/13,
October 2006), which is available on FRA’s Web site.
By making the criteria in this section consistent with those in § 213.333 in
subpart G, the rule makes it easier for a track owner or railroad to comply with
GRMS requirements regardless of the class of track.
110(g)
The GRMS vehicle shall be capable of producing output reports that
provide a trace, on a constant-distance scale, of all parameters specified in
paragraph (l) of this section.
110(h)
The GRMS vehicle shall be capable of providing an exception report
containing a systematic listing of all exceptions, by magnitude and location, to
all the parameters specified in paragraph (l) of this section.
110(i) The exception reports required by this section shall be
provided to the appropriate person designated as fully qualified under §213.7
prior to the next inspection required under §213.233.
Guidance:
Paragraphs
(g), (h), and (i) require that GRMS vehicles be capable of producing a
stripchart of all the parameters specified in paragraph (l) of this section, as
well as a printed exception report listing, by magnitude and location, all
exceptions from these parameters. The exception report listing must be provided
to the appropriate persons designated as fully qualified under § 213.7 prior to
the next inspection required under § 213.233 of the TSS.
Since the premise behind GRMS technology is to identify areas of weak gage
restraint that either need immediate attention or must be continually monitored
until the next GRMS inspection, the exception report listing must be retained
and be available for review by the § 213.7 inspection personnel. FRA inspectors
will obtain, or have access to, this exception report when conducting regular
compliance inspections over GRMS designated line segments.
110(j) The track owner shall institute the necessary procedures
for maintaining the integrity of the data collected by the GRMS and PTLF
systems. At a minimum, the track owner shall–
(1) Maintain and make available to the Federal Railroad
Administration documented calibration procedures on each GRMS vehicle which, at
a minimum, shall specify a daily instrument verification procedure that will
ensure correlation between measurements made on the ground and those recorded by
the instrumentation with respect to loaded and unloaded gage parameters; and
(2) Maintain each PTLF used for determining compliance with the
requirements of this section such that the 4,000-pound reading is accurate to
within five percent of that reading.
Guidance: This
paragraph requires the track owner to institute procedures that will ensure the
integrity of data collected by the GRMS and PTLF systems. Track owners must
maintain documented calibration procedures on each GRMS vehicle and make them
available upon request from an FRA representative. A daily instrument
verification procedure is required to ensure that measurements of loaded and
unloaded gage recorded by the instrumentation correlate to actual field
measurements. Track owners must also develop and implement the necessary PTLF
inspection and maintenance procedures so that the 4,000-pound reading is
accurate within plus or minus 5 percent.
110(k) The track owner shall provide training in GRMS technology
to all persons designated as fully qualified under §213.7 and whose territories
are subject to the requirements of this section. The training program shall be
made available to the Federal Railroad Administration upon request. At a
minimum, the training program shall address--
(1) Basic GRMS procedures;
(2) Interpretation and handling of exception reports generated
by the GRMS vehicle;
(3) Locating and verifying defects in the field;
(4) Remedial action requirements;
(5) Use and calibration of the PTLF; and
(6) Recordkeeping requirements.
Guidance:
This
paragraph recognizes the need for persons designated as fully qualified under §
213.7, and whose territories are subject to the requirements of this section, to
receive training on the implementation of GRMS technology. The track owner
therefore is required to develop a formal GRMS training program that must be
made available to FRA upon request. The training of affected employees is
another "triggering event" that must be satisfied prior to a line
segment being designated as GRMS territory under this section.
The training program must provide detailed instruction on the specific
areas identified in this paragraph. In particular, the training must address
basic GRMS operational procedures, interpretation and handling of exception
reports, how to locate and verify GRMS defects in the field, remedial action
requirements to be initiated when defects are verified, how to use and calibrate
the PTLF, and the recordkeeping requirements associated with the implementation
of GRMS technology.
The requirement for GRMS training applies to fully qualified § 213.7
personnel under paragraphs (a) and (b) who are going to be subject to the
requirements of this section. This is not to say that all fully qualified §
213.7 personnel need this training (e.g., welder foreman, production gang
foreman, etc.). It is also not necessary for all fully qualified § 213.7
personnel who receive the GRMS training to be issued PTLFs. However, if
circumstances arise where they need a PTLF, they should have access to one and
be trained in how to use it and interpret the results.
The track owner must also take into consideration any relief personnel,
newly qualified personnel, or personnel transferred from non-GRMS territory into
a GRMS territory, which will be subject to the GRMS requirements. These
personnel must be provided with sufficient instructions and training that enable
them to demonstrate to the track owner that they know and understand the
requirements of this section.
110(l) The GRMS record of lateral restraint shall identify two
exception levels. At a minimum, the track owner shall initiate the required
remedial action at each exception level as defined in the following table–
Guidance: The VTI final
rule has corrected the table to renumber the remedial action specified for a
second level exception. The remedial action has been designated as (1), (2), and
(3) in the "Remedial action required" column, to be consistent with
the remedial action specified for a first level exception. This paragraph
specifies the parameters and threshold levels
required to be reported as a record of lateral restraint following an inspection
by a GRMS vehicle. The regulation requires that two levels of exceptions be
reported during the GRMS inspection. Specific remedial actions are required for
each level, as identified in the "Remedial action required" column.
First level exceptions are required to be immediately protected by a 10 mph
speed restriction until verification and corrective action can be instituted.
Second level exceptions are to be monitored and maintained within the PTLF
criteria outlined in paragraph (m) of this section.
The prior knowledge criteria
is satisfied for those locations that are identified as first or second level
exceptions on the record of lateral restraint which is generated following each
GRMS inspection. Where field inspections conducted between GRMS inspections
reveal an exception location that does not comply with either the track strength
requirement or the gage requirement that are identified in paragraph (m) of this
section, the inspector should consider recommending civil penalties. For
locations that do not comply with the requirements of paragraph (m), and have
not been identified on the record of lateral restraint as either a first or
second level exception, the inspector shall exercise discretion to determine
whether or not civil penalties should be recommended.
Footnote 2 in the table
recognizes that typical good track will increase in total gage by as much as
one-quarter inch due to outward rail rotation under GRMS loading conditions.
Accordingly, for Class 2 and Class 3 track, the GRMS loaded track gage values
are also increased by one-quarter inch to a maximum of 58 inches. GRMS loaded
track gage values in excess of 58 inches must always be considered first level
exceptions. This ¼-inch increase in gage applies only to GRMS loaded gage, and
does not apply to PTLF gage measurements or to measurements made by more
traditional methods.
110(m) Between GRMS inspections, the PTLF may be used as an
additional analytical tool to assist fully qualified § 213.7 individuals in
determining compliance with the crosstie and fastener requirements of § 213.109 and
§ 213.127. When the PTLF is used, whether as an additional
analytical tool or to fulfill the requirements of paragraph (l), it shall be
used subject to the following criteria–
(1) At any location along the track that the PTLF is applied,
that location will be deemed in compliance with the crosstie and fastener
requirements specified in § 213.109
and § 213.127
provided that–
(i) The total gage widening at that
location does not exceed
⅝ inch when increasing the
applied force from 0 to 4,000 pounds; and
(ii) The gage of the track under 4,000 pounds of applied force
does not exceed the allowable gage prescribed in §213.53(b) for the class of
track.
(2) Gage widening in excess of
⅝ inch shall constitute a deviation
from Class 1 standards.
(3) A person designated as fully qualified under
§213.7 retains
the discretionary authority to prescribe additional remedial actions for those
locations, which comply with the requirements of paragraph (m)(1)(i) and (ii) of
this section.
(4) When a functional PTLF is not available to a fully qualified
person designated under §213.7, the criteria for determining crosstie and
fastener compliance shall be based solely on the requirements specified in §213.109 and
§213.127.
(5) If the PTLF becomes non-functional or is missing, the track
owner will replace or repair it before the next inspection required under §213.233.
(6) Where vertical loading of the track is necessary for contact
with the lateral rail restraint components, a PTLF test will not be considered
valid until contact with these components is restored under static loading
conditions.
Guidance: While
the remedial action table in paragraph (l) requires the use of the PTLF to
measure compliance with the lateral restraint and gage requirements at
identified exception locations in GRMS territory, paragraph (m) also provides
for the use of a PTLF as an additional analytical tool by fully qualified §
213.7 individuals at other locations in GRMS territory. Paragraph (m) also
describes the manner in which a PTLF must be used in GRMS territory, whether it
is being used as an additional analytical tool or being used to meet the
remedial action requirements set forth in paragraph (l). Compliance with §§
213.109 and 213.127 will be demonstrated when a PTLF is applied and (1) the
total gage widening at that location does not exceed five-eighths inch when
increasing the applied force from 0 to 4,000 pounds; and (2) the gage of the
track measured under 4,000 pounds of applied force does not exceed the allowable
gage prescribed in § 213.53(b) of this section for the class of track involved.
Gage widening in excess of five-eighths inch shall constitute a deviation from
Class 1 standards.
At locations where compliance with the crosstie and rail fastener
requirements have been demonstrated through the use of a PTLF, a fully qualified
§ 213.7 individual retains the discretionary authority to prescribe additional
remedial actions, such as the placement of speed restrictions, if the individual
deems it necessary. FRA inspectors will determine compliance with the crosstie
and fastener requirements for gage restraint solely on the basis of the PTLF
measurements.
Where crossties are found to be so severely split or plate-cut to the extent
that they are incapable of providing adequate vertical support, and conditions
have degraded to the point where track surface conditions are approaching the
allowable limit for the class of track, inspectors shall continue to consider
writing a defect. In such a case use 213 defect code 0109B2, "crossties not
effectively distributed to support a 39-foot segment of track." Inspectors
should record the track surface geometry condition as well as the contributing
condition of the crossties in the description column.
When a functional PTLF is not available to a fully qualified § 213.7
individual during a scheduled inspection under § 213.233 of this part, the
track owner must repair or replace the PTLF prior to the next inspection
required under § 213.233, or crosstie and rail fastener compliance will be
based solely on the requirements specified in §§ 213.109 and 213.127.
At locations where crosstie or rail fastening compliance is questioned and
vertical loading of the track structure is necessary to restore contact with the
lateral rail restraint components, the crossties must be raised until lateral
restraint contact is restored and a PTLF measurement must then be made.
If the track owner fails to immediately restore contact between the rail and
the fastening system so that a valid PTLF test can be performed, this non-action
will in effect remove this location from the GRMS standard and the inspector
will determine compliance based on §§ 213.109 and 213.127.
Likewise, where gage rods have been installed which preclude a valid PTLF
test to determine gage restraint of crossties and fasteners, this action will in
effect remove the location from the
GRMS
standard and the inspector will determine compliance based on §§ 213.109 and
213.127.
110(n) The track owner shall maintain a record of the two most
recent GRMS inspections at locations which meet the requirements specified in §213.241(b). At a minimum, records shall indicate the following--
(1) Location and nature of each First Level exception; and
(2) Nature and date of remedial action, if any, for each
exception identified in paragraph (n)(1) of this section.
Guidance:
This
paragraph requires the track owner to maintain a record of the two most recent
GRMS inspections at locations meeting the requirements specified in §
213.241(b). The records must indicate the location and nature of each First
Level exception, and the nature and date of initiated remedial action, if any,
for each First Level exception. First Level exceptions are described in the
Remedial Action Table in paragraph (l).
The record required under paragraph (n) is also the official record of
lateral restraint and needs to identify both exception levels; however, the
remedial action taken is required to be shown only for First Level exceptions.
Records will be maintained at locations that meet the requirements specified in
§ 213.241(b).
110(o) The inspection interval for designated GRMS line segments
shall be such that--
(1) On line segments where the annual tonnage exceeds two
million gross tons, or where the maximum operating speeds for passenger trains
exceeds 30 m.p.h., GRMS inspections must be performed annually at an interval
not to exceed 14 months; or
(2) On line segments where the annual tonnage is two million
gross tons or less and the maximum operating speed for passenger trains does not
exceed 30 m.p.h., the interval between GRMS inspections must not exceed 24
months.
Guidance. Paragraph (o)
details the GRMS inspection requirements which is illustrated in the following
table:
[1] The maximum interval of 14 months is intended to provide
some flexibility for scheduling when it may not be possible to schedule annual
inspections within the same calendar month each year.
[2] This extended frequency is an attempt to make the technology
more accessible to short line operators who may not have the financial or
equipment resources available to larger railroads. For example, a GRMS
inspection may be scheduled at up to 24-month intervals if the railroad had 2
million annual tons or less and passenger trains were not authorized to operate
at more than 30 mph.
(1) Gage Restraint Measurement System (GRMS) means a track
loading vehicle meeting the minimum design requirements specified in this
section.
(2) Gage Widening Ratio (GWR)
means the measured gage widening, which is the difference between loaded and
unloaded gage, at the applied loads, projected to reference loads of 16 kips of
lateral force and 33 kips of vertical force.
(3) L/V ratio means the numerical ratio of lateral load applied
at a point on the rail to the vertical load applied at that same point. GRMS
design requirements specify an L/V ratio of between 0.5 and 1.25. GRMS vehicles
using load combinations developing L/V ratios which exceed 0.8 must be operated
with caution to protect against the risk of wheel climb by the test wheelset.
(4) Load severity means the amount of lateral load applied to
the fastener system after friction between rail and tie is overcome by any
applied gage-widening lateral load.
(5) Loaded Track Gage (LTG) means the gage measured by the GRMS
vehicle at a point no more than 12 inches from the lateral load application
point.
(6) Portable Track Loading Fixture (PTLF) means a portable track
loading device capable of applying an increasing lateral force from 0 to 4,000
pounds on the web/base fillet of each rail simultaneously.
(7) Projected Loaded Gage (PLG) means an extrapolated value for
loaded gage calculated from actual measured loads and deflections. PLG 24 means
the extrapolated value for loaded gage under a 24,000 pound lateral load and a
33,000 pound vertical load.
(8) Unloaded Track Gage (UTG) means the gage measured by the
GRMS vehicle at a point no less than 10-feet from any lateral or vertical load.
[66 FR 1899, Jan. 10, 2001; 66 FR 8372, Jan. 31, 2001, as
amended at 78 FR 16102, Mar. 13, 2013]
Guidance. This paragraph
prescribes a list of definitions of terms essential to the implementation of
GRMS technology.
A well-documented pattern of repeated or widespread deviations
from the requirements of this section by the track owner will effectively
terminate the options afforded by this section. The affected track would then
become subject to the requirements of § 213.109 and
§ 213.127.
(a) When an owner of track to which this part applies learns,
through inspection or otherwise, that a rail in that track contains any of the
defects listed in the following table, a person designated under §213.7 shall
determine whether or not the track may continue in use. If he determines that
the track may continue in use, operation over the defective rail
is not permitted until -- (1) The rail is replaced; or (2) The
remedial action prescribed in the table is initiated.
Notes:
A. Assign person designated under §213.7 to visually supervise
each operation over defective rail.
A2. Assign person designated under §213.7 to make visual
inspection. After a visual inspection, that person may authorize operation to
continue without continuous visual supervision at a maximum of 10 m.p.h. for up
to 24 hours prior to another such visual inspection or replacement or repair of
the rail.
B. Limit operating speed over defective rail to that as
authorized by a person designated under §213.7(a), who has at least one year of
supervisory experience in railroad track maintenance. The operating speed cannot
be over 30 m.p.h. or the maximum allowable speed under §213.9 for the class of
track concerned, whichever is lower.
C. Apply joint bars bolted only through the outermost holes to
defect within 20 days after it is determined to continue the track in use. In
the case of Classes 3 through 5 track, limit operating speed over defective rail
to 30 m.p.h. until joint bars are applied; thereafter, limit speed to 50 m.p.h.
or the maximum allowable speed under §213.9 for the class of track concerned,
whichever is lower. When a search for internal rail defects is conducted under
§213.237, and defects are discovered in Classes 3 through 5 which require
remedial action C, the operating speed shall be limited to 50 m.p.h., or the
maximum allowable speed under §213.9 for the class of track concerned,
whichever is lower, for a period not to exceed 4 days. If the defective rail has
not been removed from the track or a permanent repair made within 4 days of the
discovery, limit operating speed over the defective rail to 30 m.p.h. until
joint bars are applied; thereafter, limit speed to 50 m.p.h. or the maximum
allowable speed under §213.9 for the class of track concerned, whichever is
lower.
D. Apply joint bars bolted only through the outermost holes to
defect within 10 days after it is determined to continue the track in use. In
the case of Classes 3 through 5 track, limit operating speed over the defective
rail to 30 m.p.h. or less as authorized by a person designated under §213.7(a),
who has at least one year of supervisory experience in railroad track
maintenance, until joint bars are applied; thereafter, limit speed to 50 m.p.h.
or the maximum allowable speed under §213.9 for the class of track concerned,
whichever is lower.
E. Apply joint bars to defect and bolt in accordance with
§213.121(d) and (e).
F. Inspect rail 90 days after it is determined to continue the
track in use.
G. Inspect rail 30 days after it is determined to continue the
track in use.
H. Limit operating speed over defective rail to 50 m.p.h. or the
maximum allowable speed under §213.9 for the class of track concerned,
whichever is lower.
I. Limit operating speed over defective rail to 30 m.p.h. or the
maximum allowable speed under §213.9 for the class of track concerned,
whichever is lower.
(1) Transverse fissure means a progressive crosswise fracture
starting from a crystalline center or nucleus inside the head from which it
spreads outward as a smooth, bright, or dark, round or oval surface
substantially at a right angle to the length of the rail. The distinguishing
features of a transverse fissure from other types of fractures or defects are
the crystalline center or nucleus and the nearly smooth surface of the
development which surrounds it.
(2) Compound fissure means a progressive fracture originating in
a horizontal split head which turns up or down in the head of the rail as a
smooth, bright, or dark surface progressing until substantially at a right angle
to the length of the rail. Compound fissures require examination of both faces
of the fracture to locate the horizontal split head from which they originate.
(3) Horizontal split head means a horizontal progressive defect
originating inside of the rail head, usually ¼ inch or more below the running
surface and progressing horizontally in all directions, and generally
accompanied by a flat spot on the running surface. The defect appears as a crack
lengthwise of the rail when it reaches the side of the rail head.
(4) Vertical split head means a vertical split through or near
the middle of the head, and extending into or through it. A crack or rust streak
may show under the head close to the web or pieces may be split off the side of
the head.
(5) Split web means a lengthwise crack along the side of the web
and extending into or through it.
(6) Piped rail means a vertical split in a rail, usually in the
web, due to failure of the shrinkage cavity in the ingot to unite in rolling.
(7) Broken base means any break in the base of the rail.
(8) Detail fracture means a progressive fracture originating at
or near the surface of the rail head. These fractures should not be confused
with transverse fissures, compound fissures, or other defects which have
internal origins. Detail fractures may arise from shelly spots, head checks, or
flaking.
(9) Engine burn fracture means a progressive fracture
originating in spots where driving wheels have slipped on top of the rail head.
In developing downward they frequently resemble the compound or even transverse
fissures with which they should not be confused or classified.
(10) Ordinary break means a partial or complete break in which
there is no sign of a fissure, and in which none of the other defects described
in this paragraph (b) are found.
(11) Damaged rail means any rail broken or injured by wrecks,
broken, flat, or unbalanced wheels, slipping, or similar causes.
(12) Flattened rail means a short length of rail, not at a
joint, which has flattened
out across the width of the rail head to a depth of ⅜ inch or
more below the rest of the rail. Flattened rail occurrences have no repetitive
regularity and thus do not include corrugations, and have no apparent localized
cause such as a weld or engine burn. Their individual length is relatively
short, as compared to a condition such as head flow on the low rail of curves.
(13) Bolt hole crack means a crack across the web, originating
from a bolt hole, and progressing on a path either inclined upward toward the
rail head or inclined downward toward the base. Fully developed bolt hole cracks
may continue horizontally along the head/web or base/web fillet, or they may
progress into and through the head or base to separate a piece of the rail end
from the rail. Multiple cracks occurring in one rail end are considered to be a
single defect. However, bolt hole cracks occurring in adjacent rail ends within
the same joint must be reported as separate defects.
(14) Defective weld means a field or plant weld containing any
discontinuities or pockets, exceeding 5 percent of the rail head area
individually or 10 percent in the aggregate, oriented in or near the transverse
plane, due to incomplete penetration of the weld metal between the rail ends,
lack of fusion between weld and rail end metal, entrainment of slag or sand,
under-bead or other shrinkage cracking, or fatigue cracking. Weld defects may
originate in the rail head, web, or base, and in some cases, cracks may progress
from the defect into either or both adjoining rail ends.
(15) Head and web separation means a progressive fracture,
longitudinally separating the head from the web of the rail at the head fillet
area.
Guidance: The remedial actions required for
defective rails specify definite time limits and speeds. The remedial actions
also allow certain discretion to the track owner for the continued operation
over certain defects. Inspectors should consider all rail defects dangerous and
care should be taken to determine that proper remedial actions have been
accomplished by the railroad. When more than one defect is present in a rail,
the defect requiring the most restrictive remedial action shall govern.
The remedial action table and specifications in the
rule address the risks associated with rail failure. These risks are primarily
dependent upon defect type and size and should not be dependent upon the manner
or mechanism that reveals the existence of the defect. Failure of the track
owner to comply with the operational (speed) restrictions, maintenance
procedures and the prescribed inspection intervals specified in this section and
§ 213.237 (Defective rails and Inspection of rail, respectively), may
constitute a violation of the TSS.
Note "A2" addresses mid-range transverse
defect sizes. This remedial action allows for train operations to continue at a
maximum of 10 mph up to 24 hours, following a visual inspection by a person
designated under § 213.7. If the rail is not replaced, another 24-hour cycle
begins.
Note "B" limits speed to that as
authorized by a person designated under § 213.7(a) who has at least 1 year of
supervisory experience in track maintenance. The qualified person has the
responsibility to evaluate the rail defect and authorize the maximum operating
speed over the defective rail based on the size of the defect and the operating
conditions; however, the maximum speed over the rail may not exceed 30 mph or
the maximum speed under § 213.9 for the class of track concerned, whichever is
lower.
Notes "C," "D," and
"H" limit the operating speed, following the application of joint
bars, to 50 m.p.h. or the maximum allowable speed under § 213.9 for the class
of track concerned, whichever is lower. When the maximum speed specified in
notes "B," "C," "D," and "H" exceeds the
current track speed, the railroad is required to record the defect. For example,
when a railroad determines that remedial action "B" is required and
the track speed already is 30 mph or less, the railroad must record the defect.
This indicates that the railroad is aware of the characteristics of the
defective rail and has designated a permissible speed in compliance with the
regulation.
When an FRA inspector discovers a defective rail
that requires the railroad representative to determine whether to continue the
track in use and to designate the maximum speed over the rail, the inspector
should inquire as to the representative's knowledge of the defect and remedial
action. If the railroad was not aware of the defect prior to the FRA inspection,
the FRA inspector should observe the actions taken by the railroad
representative to determine compliance. If the railroad had previously found the
defective rail, the FRA inspector should confirm the proper remedial action was
taken. During records inspections, the FRA inspector should confirm that the
defects were recorded and proper remedial actions were taken.
The remedial action table for defects failing in the
transverse plane (transverse and compound fissures, detail and engine burn
fractures, and defective welds) specifies a lower limit range base of 5 percent
of the railhead cross-sectional area. If a transverse defect is reported to be
less than 5 percent, the track owner is not legally bound to provide corrective
action under the TSS. Defects reported less than 5 percent are not consistently
found during rail breaking routines and therefore, defect determination within
this range is not always reliable.
Transverse and compound fissure defects, weakened
between 5 and 70 percent of cross-sectional head area require remedial action
(note B). Defects in the range between 70 and less than 100 percent of
cross-sectional head area require remedial action (note A2), as prescribed.
Defects that affect 100 percent of the cross-sectional head area require
remedial action (note A) as prescribed, the most restrictive. Inspectors should
be aware that transverse and compound fissures are defects that fail in the
transverse plane and are characteristic of rail that has not been control-cooled
(normally rolled prior to 1936).
Defects identified and grouped as detail fracture,
engine burn fracture, and defective welds, will weaken and also fail in the
transverse plane. Detail fractures are characteristic of control-cooled rail
[usually indicated by the letters CC or CH on the rail brand (i.e., 1360 RE CC
CF&I 1982 1111). Their prescribed remedial action relates to a low range
between 5 and 25 percent and a mid-range between 25 and 80 percent, for note (C)
and note (D), respectively. Those defects require joint bar applications and
operational speed restrictions within certain time frames. Defects extending
less than 100 and more than 80 percent require a visual inspection. If the rail
is not replaced, effectively repaired, or removed from service, an elective
would be to restrict operation to a maximum of 10 mph for up to 24 hours, then
perform another visual inspection.
The second sentence in remedial action note (C)
addresses defects which are discovered in Classes 3 through 5 track during an
internal rail inspection required under § 213.237, and which are determined not
to be in excess of 25 percent of the rail head cross-sectional area. For these
specific defects, a track owner may operate for a period not to exceed 4 days,
at a speed limited to 50 mph or the maximum allowable speed under § 213.9 for
the class of track concerned, whichever is lower. If the defective rail is not
removed or a permanent repair is not made within 4 days of discovery, the speed
is limited to 30 mph, until joint bars are applied or the rail is replaced.
The requirements specified in this second paragraph
are intended to promote better utilization of rail inspection equipment and
therefore maximize the opportunity to discover rail defects, which are
approaching service failure size. The results of FRA’s research indicate that
defects of this type and size range have a predictable slow growth life.
Research further indicates that even on the most heavily utilized trackage in
use today, defects of this type and size are unlikely to grow to service failure
size in four days.
In the remedial action table, all longitudinal
defects are combined within one group subject to identical remedial actions
based on their reported size. These types of longitudinal defects all share
similar growth rates and the same remedial actions are appropriate to each type.
Defective rails categorized as horizontal split
head, vertical split head, split web, piped rail, and head-web separation, are
longitudinal in nature. When any of this group of defects is more than 1 inch,
but not more than 2 inches, the remedial action initiated, under note (H), is to
limit train speed to 50 mph, and note (F) requires reinspecting the rail in 90
days, if deciding operations will continue. Defects in the range of more than 2
inches, but not more than 4 inches, require complying with notes (I) and (G),
speed is limited to 30 mph and the rail reinspected in 30 days, if they decide
operations will continue. When any of the five defect types exceed a length of 4
inches, under note (B) a person designated under § 213.7(a) who decides
opertions will continue must authorize the operating speed, up to but not to
exceed 30 mph, under note (B).
Another form of head-web separation, often referred
to as a "fillet cracked rail," is the longitudinal growth of a crack
in the fillet area, usually on the gage side of the outer rail of a curve. The
crack may not extend the full width between the head and the web, but it is
potentially dangerous. Evidence of fillet cracking is a hairline crack running
beneath the head of rail with "bleeding" or rust discoloration. Fillet
cracks often result from improper superelevation or from stress reversal as a
result of transposing rail. The use of a mirror is an effective aid in examining
rail and the determination of head-web cracks or separation in the body of the
rail.
A "bolt hole crack" is a progressive
fracture originating at a bolt hole and extending away from the hole, usually at
an angle. They develop from high stress risers, usually initiating as a result
of both dynamic and thermal responses of the joint bolt and points along the
edge of the hole, under load. A major cause of this high stress is improper
field drilling of the hole. Excessive longitudinal rail movement can also cause
high stress along the edge of the hole.
When evaluating a rail end, which has multiple bolt
hole cracks, inspectors will determine the required remedial action based on the
length of the longest individual bolt hole crack.
Under note (H) and (F), the remedial action for a
bolt hole crack, more than one-half inch, but not more than 1 inch, if the rail
is not replaced, is to limit speed to 50 mph, or the maximum allowable under §
213.9 for the class of track concerned, whichever is lower, then reinspect the
rail in 90 days, if operations will continue.
For bolt hole cracks greater than 1 inch, but not
exceeding 1½ inches, notes (H) and (G) apply. These rails are required to be
limited to 50 mph and reinspected within 30 days. For a bolt hole crack
exceeding 1½ inches, a person qualified under § 213.7(a) may elect to
designate a speed restriction, which cannot exceed 30 mph, or the maximum
allowable under § 213.9 for the class of track concerned, whichever is lower.
Under notes (F) and (G), where corrective action
requires rail to be reinspected within a specific number of days after
discovery, several options for compliance may be exercised depending on the
nature of the defect. For those defects, which are strictly internal and are not
yet visible to the naked eye, the only option would be to perform another
inspection with rail flaw detection equipment, either rail-mounted or hand-held.
For defects that are visible to the naked eye and therefore measurable, a visual
inspection or an inspection with rail flaw detection equipment are acceptable
options. For certain defects enclosed within the joint bar area, such as bolt
hole cracks and head-web separations, the joint bars must be removed if a visual
reinspection is to be made.
The reinspection prescribed in notes (F) and (G)
must be performed prior to the expiration of the 30 or 90 day interval. If the
rail remains in track and is not replaced, the reinspection cycle starts over
with each successive reinspection unless the reinspection reveals the rail
defect to have increased in size and has therefore become subject to a more
restrictive remedial action. This process continues indefinitely until the rail
is removed from track.
Where corrective action requires rail to be
reinspected within a specific number of days after discovery, the track owner
may exercise several options for compliance. One option would be to perform
another inspection with rail flaw detection equipment, either rail-mounted or
hand-held. Another option would be to perform a visual inspection where the
defect is visible and measurable. In the latter case, for certain defects
enclosed within the joint bar area such as bolt hole breaks, removal of the
joint bars will be necessary to comply with the reinspection requirement. If
defects remain in track beyond the reinspection interval, the railroad must
continue to monitor the defects and take the appropriate actions as required in
the remedial action table.
A broken base can result from improper bearing of
the base on a track spike or tie plate shoulder, and from over crimped anchors,
or it may originate in a manufacturing flaw. With today’s higher axle loads,
inspectors can anticipate broken base defects in 75-pound, and smaller, rail
sections with an irregular track surface, especially on the field side. For any
broken base discovered that is more than 1 inch, but less than 6 inches in
length, the remedial action (note D) is to apply joint bars bolted through the
outermost holes to defect within 10 days, if operations will continue. In
Classes 3 through 5 track, the operating speed must be reduced to 30 mph or
less, as authorized by a person under § 213.7(a), until joint bars are applied.
After that, operating speed is limited to 50 mph or the maximum allowable under
§ 213.9 for the class of track concerned, whichever is lower.
Under note D, there are several acceptable
"outermost hole" bolting arrangements for joint bars centered on a
rail defect. See the following figure for an illustration of acceptable bolting
arrangements. In all cases, railroads may not drill a bolt hole next to a defect
that is being remediated with the application of joints bars (pursuant to note
D). The reason for not drilling next to the defect is to prevent the propagation
of the crack into the hole closest to the defect.
A broken base in excess of 6 inches requires the
assignment of a person designated under § 213.7 to visually supervise each
train operation over the defective rail. The railroad may apply joint bars to
the defect and bolt them in accordance with §§ 213.121(d) and (e) and
thereafter must limit train operations to 30 mph or the maximum allowable under
§ 213.9 for the class of track concerned, whichever is lower. As reference, the
dimensions between the outermost holes of a 24-inch joint bar vary between
approximately 15 and 18 inches and a 36-inch joint bar approaches 30 inches.
Inspectors should point out to the track owner that
broken bases nearing these dimensions may negate the purpose for which the joint
bars are applied. A broken base rail may be caused by damage from external
sources, such as rail anchors being driven through the base by a derailed wheel.
It is improper to consider them "damaged rail," as this defect is
addressed by more stringent provisions applicable to broken base rails, under
note (A) or (E) and (I).
Damaged rail can result from flat or broken wheels,
incidental hammer blows, or derailed or dragging equipment. Reducing the
operational speed in Classes 3 through 5 track to 30 mph until joint bars are
applied, lessens the impact force imparted to the weaken area. Applying joint
bars under note (D) ensures a proper horizontal and vertical rail end alinement
in the event the rail fails.
Flattened rails (localized collapsed head rail) are
also caused by mechanical interaction from repetitive wheel loadings. FRA and
industry research indicate that these occurrences are more accurately
categorized as rail surface conditions, not rail defects, as they do not, in
themselves, cause service failure of the rail. Although it is not a condition
shown to affect the structural integrity of the rail section, it can result in
less than desirable dynamic vehicle responses in the higher speed ranges. The
flattened rail condition is identified in the table, as well as in the
definition portion of § 213.113(b), as being three-eighths inch or more in
depth
below the rest of the railhead and 8 inches or more in
length. As the defect becomes more severe by a reduced rail head depth, wheel
forces increase.
The rule addresses flattened rail in terms of a
specified remedial action for those of a certain depth and length. Those
locations meeting the depth and length criteria shall be limited to an operating
speed of 50 mph or the maximum allowable under § 213.9 for the class of track
concerned, whichever is lower.
"Break out in rail head" is defined as a
piece that has physically separated from the parent rail. Rail defects meeting
this definition are required to have each operation over the defective rail
visually supervised by a person designated under § 213.7. Inspectors need to be
aware that this definition has applicability across a wide range of rail
defects, as indicated in the Remedial Action Table. Where rail defects have not
progressed to the point where they meet the definition of a break out, but due
to the type, length and location of the defect, they present a hazard to
continued train operation, inspectors should determine what remedial actions, if
any, track owner should institute.
The following are two rail head break out examples
where the "A" corrective action would be necessary:
Example One: There is a bolt hole break where the head
of the rail is totally separated from the parent rail (either tight or loose),
but that piece of rail will not physically lift out of the joint bars by hand.
The inspector might determine that the separation was total by the fact that the
separated piece rattled when tapped. It is important that railroads take the
appropriate remedial action in this situation, because it is potentially very
unsafe. It is impossible to know what will happen when the next train operates
over this defect. That train could cause the piece to become so loose that it
comes out of the place, cocks at an angle and causes a wheel to ramp up.
Example Two: A vertical split head defective rail where
rail head separation is apparent because the inspector can determine that a
physical separation has occurred through the rail head, but the rail head has
not entirely separated over the entire length of the defect.
The issue of "excessive rail wear" continues
to be evaluated by the Rail Integrity Task Force. The FRA believes that
insufficient data exists at this time to indicate that parameters for this
condition should be proposed as a minimum standard.
The Sperry Rail Service prints an excellent reference
manual on rail defects. Inspectors are expected to be conversant with rail
defect types, appearance, growth, hazards, and methods of detection.
Some railroads apply safety "weld straps" to
thermite type field welds. These straps do not provide the same support of a
joint bar. They would provide only limited support if a weld were to break under
a train movement and as such, they do not comply with the provisions of
corrective actions C, D, or E (installation of joint bars). Only a joint bar
with full contact with the bottom of the rail head and rail base [see § 213.121
(a)] and with a manufactured relief for the weld material would comply with
corrective actions C, D, or E.
When an FRA inspector finds a rail defect that appears
to originate from fatigue at a bond wire attachment weld, the inspector should
cite the railroad for 213 defect code 0113B.
Inspectors must also identify in their narrative the
type of the rail defect (e.g., defective weld, detail fracture, etc.). FRA has
added this defect code based on a National Transportation Safety Board (NTSB)
recommendation arising from the NTSB investigation of a February 9, 2003,
Canadian National Railway (CN) derailment in Tamaroa, Illinois. The NTSB
determined that the probable cause of this accident was CN's placement of bond
wire welds on the head of the rail just outside the joint bars, where untempered
martensite associated with the welds led to fatigue cracking that, because of
increased stresses associated with known soft ballast conditions, rapidly
progressed to rail failure.
Any mismatch of rails at joints may not be more than that
prescribed by the following table –
Guidance. Use a
straightedge to determine the mismatch by holding the straightedge
longitudinally along the higher rail (tread) or along the gage side
(five-eighths inch down from the running surface) of the rail. Measure the
distance directly between the straightedge and the rail. Disregard plastic
overflow (gage side rail edge lipping), if any.
One example of mismatch occurs when a section of a rail is
placed in the track where the existing rail head is gage- and/or treadworn.
Mismatch can also occur when the joint bars are loose. However, if the loose
bars do not result in mismatch exceeding the thresholds under this section,
report the defect as loose joint bars (see § 213.121).
The standards prescribe both tread and gage mismatch thresholds.
A mismatch may result in high impact forces especially at higher speeds. If a
mismatch in excess of the allowable results in significant rail end damage, a
violation should be considered.
Particular attention should be given to the mismatch on the gage
side of a rail. A thin flange, skewed truck, or combination of both may cause a
wheel to climb, particularly on the outer rail of a curve. Figure 18 shows the
proper method to measure gage and tread mismatch.
§ 213.118 Continuous welded rail (CWR); plan review and
approval.
118(a) Each track owner with track constructed of CWR shall have
in effect and comply with a plan that contains written procedures which address:
the installation, adjustment, maintenance, and inspection of CWR; inspection of
CWR joints; and a training program for the application of those procedures.
118(b) The track owner shall file its CWR plan with the FRA
Associate Administrator for Railroad Safety/Chief Safety Officer (Associate
Administrator). Within 30 days of receipt of the submission, FRA will review the
plan for compliance with this subpart. FRA will approve, disapprove or
conditionally approve the submitted plan, and will provide written notice of its
determination.
118(c) The track owner’s existing plan shall remain in effect
until the track owner’s new plan is approved or conditionally approved and is
effective pursuant to paragraph (d) of this section.
118(d) The track owner shall, upon receipt of FRA’s approval
or conditional approval, establish the plan’s effective date. The track owner
shall advise in writing FRA and all affected employees of the effective date.
118(e) FRA, for cause stated, may, subsequent to plan approval
or conditional approval, require revisions to the plan to bring the plan into
conformity with this subpart. Notice of a revision requirement shall be made in
writing and specify the basis of FRA’s requirement. The track owner may,
within 30 days of the revision requirement, respond and provide written
submissions in support of the original plan. FRA renders a final decision in
writing. Not more than 30 days following any final decision requiring revisions
to a CWR plan, the track owner shall amend the plan in accordance with FRA’s
decision and resubmit the conforming plan. The conforming plan becomes effective
upon its submission to FRA.
Guidance: All CWR
plans must be submitted to FRA for review by the Track Division and then
approval by the Associate Administrator for Railroad Safety/Chief Safety Officer.
FRA reviews each plan for compliance with §§ 213.119(a) through (l).
Regional track specialists may be requested to provide recommendations
concerning the comprehensiveness of those procedures.
When conducting track inspections, an FRA inspector
should have with him the most recent copy of a railroad’s CWR plan. This is
important because it will enable the inspector to perform a proper inspection
and determine compliance with the plan. Finalized CWR plans are posted on the
FRA secured Web site for the inspector’s review and enforcement. If an
inspector discovers substantial discrepancies between the official plan on file
at FRA headquarters and the plan in the field (or that there are substantial
discrepancies between the official plan on file with FRA and a railroad field
manual), the inspector should notify the regional Track specialist.
FRA may also conditionally approve a plan. There might
be instances where it would be beneficial for the agency to conditionally
approve a plan. For example, FRA might decide that a plan should be approved,
but might need to look into new technology proposed in the plan. FRA reserves
the ability to later approve or disapprove a plan that it has formally
conditionally approved.
A track owner may update or modify CWR procedures as
necessary, but must resubmit any new or modified plan to FRA pursuant to §
213.118. Until the new plan is approved or conditionally approved and effective
pursuant to paragraph (d), the track owner’s existing plan will remain in
effect.
§ 213.119 Continuous welded rail (CWR); plan contents.
Guidance, General: In
addition to safety-critical procedures listed in this section, the railroad may
decide to include procedures based on administrative or economic considerations.
For example, a railroad may choose to include instructions that limit the use of
worn secondhand replacement rail because of an economic concern about the length
of time that it might take to perform a satisfactory weld. The railroad may also
include specific actions in their procedures that are to be taken when
installation or maintenance work does not comply with its overall procedures.
Recording an activity that does not conform to the railroad’s
CWR procedures does not provide the railroad with indefinite relief from
responsibility for compliance when its procedures are not followed. Continued
noncompliance may lead to an unsafe condition. The recordkeeping procedure is
intended to provide a safety net by flagging those activities of noncompliance,
which, if not brought into compliance in a timely manner, could lead to an
unsafe condition. For example, CWR installed in the winter months without
adequate rail anchors as prescribed by the written procedures and discovered in
late summer would clearly be a deficient condition, regardless of if it was
recorded. When in doubt as to what activities are considered safety related, the
inspector should consult with the regional Track specialist.
Whenever conducting inspections on a railroad and that activity
includes observation of CWR, FRA inspectors are to include only one “CWRP”
unit on the header of their Railroad Inspection System for Personal Computers (RISPC)
inspection report. Record one CWRP unit, regardless of the amount of CWR mileage
inspected. Record the actual track mileage units using the activity codes MTH,
MTW, etc. When a defect is taken for any aspect of § 213.119, FRA inspectors
are to also designate CWRP for the line item “activity” cell. In addition,
inspectors are to use CWRP in each line item activity cell when performing
records inspections and recording deficiencies concerning CWR joint records.
The definition of a “buckling incident” explains the
industry definition for such an event. However, the rule recognizes the
importance of conditions that are precursors to buckles.
The two failure modes associated with track constructed with CWR
are track buckles and pull-aparts. A track buckle is considered the more serious
of the two and is characterized by the formation of a large lateral misalinement
caused by:
• High compressive forces
in the rail (thermal and mechanical loads).
• Vehicle loads (a dynamic
“wave” uplift and lateral vs. vertical ratios).
The track owner shall comply with the contents of the CWR plan
approved or conditionally approved under § 213.118. The plan shall contain the
following elements—
119(a) Procedures for the installation and adjustment of CWR
which include—
(1) Designation of a desired rail installation temperature range
for the geographic area in which the CWR is located; and
(2) De-stressing procedures/methods which address proper
attainment of the desired rail installation temperature range when adjusting CWR.
Guidance: Track owners
with track constructed of CWR are required to have in effect and comply with a
CWR plan. This includes track owners who operate entirely on CWR track that has
been designated as excepted track, pursuant to §
213.4. The procedures under §
213.119 do not apply to excepted track. (See § 213.5(b)). However, where a
railroad designates a segment of track as excepted, it still must meet the
requirements of at least Class 1 track for any portion of that track that is:
(1) located within 30 feet of an adjacent track that is subjected to
simultaneous use at speeds in excess of 10 mph, or (2) located on a bridge or on
a public street or highway and there are trains with placarded cars. (See § 213.4(d).)
Railroads typically establish a desired rail installation
temperature range for the geographical area that is higher than the annual mean
temperature. This higher installation temperature will account for the expected
reduction of the force-free temperature caused by track maintenance, train
traffic, and other factors. As reference, the term for this expected occurrence
is “rail neutral temperature shift.” A railroad’s failure to establish a
designated installation temperature range for a specific territory is addressed
under § 213.119(a).
119(b) Rail anchoring or fastening requirements that will
provide sufficient restraint to limit longitudinal rail and crosstie movement to
the extent practical, and specifically addressing CWR rail anchoring or
fastening patterns on bridges, bridge approaches, and at other locations where
possible longitudinal rail and crosstie movement associated with normally
expected train-induced forces, is restricted.
119(c)
CWR joint installation and maintenance procedures which
require that—
(1) Each rail shall be bolted with at least two bolts at each
CWR joint;
Guidance: The track
inspector should determine that any joints installed in CWR or connecting to CWR
must have at least two bolts in each rail end, a minimum of four bolts installed
in the joint bars, if not field welded at the time of installation. § 213.121(e).
This requirement serves as a reminder to track owners that they
cannot create their own joint bolt requirements in their CWR plans that are less
restrictive than those specified in the TSS.
(2) In the case of a bolted joint installed during CWR
installation after October 21, 2009, the track owner shall either, within 60
days—
(i) Weld the joint;
(ii) Install a joint with six bolts; or
(iii) Anchor every tie 195 feet in both directions from the
joint; and
Guidance: This section
applies to major installations of CWR, such as more than 400 feet. It is not
intended for plug rails. Note that the applicability date published in the final
rule for this section (August 25, 2009) was corrected via the amendment
published on October 21, 2009, at 74 FR 53889.
(3) In the case of a bolted joint in CWR experiencing service
failure or a failed bar with a rail gap present, the track owner shall either—
Guidance: This section
addresses CWR joints that experience a failure with a rail gap present. The
definition for rail gap for this section is that the rail is under tension. An
example of a joint failure under tension is a joint where the rail ends could
not be pulled back together manually, as with the use of a drift pin, or if
mechanical or thermal assistance is needed. A remedial action from § 213.119(c)(3) must be taken. Check for evidence of tension (such as bent and
broken bolts) or application of thermal force (heat from repair rope, sawdust,
or flammable mix).
(i) Weld the joint;
Guidance: The rail is
welded at the time the joint is repaired.
(ii) Replace the broken bar(s), replace the broken bolts, adjust
the anchors and, within 30 days, weld the joint;
Guidance: The 30-day time
limit is only to allow the railroad adequate time to gather resources to weld
the joint. If a CWR joint becomes battered before a repair can be completed and
the track owner decides to cut in a plug rail to remove the battered joint, the
track must immediately be brought into compliance as specified in § 213.121(e).
The 30-day time limit starts from the original joint installation date for both
joints. The remedial action 30-day period does not begin again when both CWR
rail joints are required to be removed. If the joints have not been welded on
the 31st day, a violation may be submitted to the track owner for failure to
take the appropriate remedial action. The track owner must have selected the
planned remedial action to be taken on the inspection report or other
documentation that may be addressed in the CWR plan at the time the defect was
discovered, and it must be documented. This written or electronic documentation
must be made available upon request by FRA during regular business hours.
(iii) Replace the broken bar(s), replace the broken bolts,
install one additional bolt per rail end, and adjust anchors;
(iv) Replace the broken bar(s), replace the broken bolts, and
anchor every tie 195 feet in both directions from the CWR joint; or
(v) Replace the broken bar(s), replace the broken bolts, add
rail with provisions for later adjustment pursuant to paragraph (d)(2) of this
section, and reapply the anchors.
Guidance: The track owner
should ensure that any rail added during the repair of a CWR pull-apart is properly adjusted back to the required safe
neutral temperature in accordance with the railroad’s CWR plan. As the rail
temperature rises, the expansion of rail increases. The track owner must have
provisions in the CWR plan to slow order the affected track and make repairs and
adjustment to bring the track into compliance. For example, in many cases, the
addition of 1 inch of rail in a 1,000-foot string of CWR will lower its rail
neutral temperature by 13 degrees.
If the remedial actions, described in §§ 213.119(c)(iii),
(iv), or (v); are used and the affected joint fails again (with a rail gap
present after the initial repair), additional, more restrictive repairs are
required. This shows that the rail tension was not adequately addressed during
the initial remedial action. CWR joints must be inspected for compliance with
additional parts of the TSS, such as tie condition, surface, rail end mismatch,
and properly fitting joint bars.
119(d) Procedures which specifically address maintaining a
desired rail installation temperature range when cutting CWR including rail
repairs, in-track welding, and in conjunction with adjustments made in the area
of tight track, a track buckle, or a pull-apart. Rail repair practices shall
take into consideration existing rail temperature so that—
(1) When rail is removed, the length installed shall be
determined by taking into consideration the existing rail temperature and the
desired rail installation temperature range; and
(2) Under no circumstances should rail be added when the rail
temperature is below that designated by paragraph (a)(1) of this section,
without provisions for later adjustment.
119(e) Procedures which address the monitoring of CWR in curved
track for inward shifts of alinement toward the center of the curve as a result
of disturbed track.
Guidance: Thermal and
mechanical loads affecting track structure are decreased by the track owner’s
adherence to the track engineering standards. Adherence to the track owner’s
standards and the CWR plan promote CWR track stability and safety. Three
engineering elements resist mechanical loads and thermal loads: lateral
resistance, longitudinal resistance, and rail neutral temperature. Track buckles
can be expected to occur predominately in the lateral dimension. Lateral
resistance is critical to being dependent upon weight and size of crosstie
material, ballast material type, shoulder width, crib content, and its level of
consolidation. As degree of curvature increases, the buckling resistance
decreases. A crosstie’s base, side (crib) friction, and ballast shoulder
resistance contribute to the overall lateral resistance sustained. In general,
each contributes (base 50 percent, side 20–30 percent, and shoulder 20–30
percent) to this resistance, but the ratios can vary depending on ballast
condition. Lateral resistance varies in location depending on the ballast
shoulder geometry, crosstie size and type, and state of ballast consolidation.
Thermal loads, by themselves, can cause a buckle and are often
called “static buckling.” However, most buckling occurs under a combination
of thermal and vehicle loads, termed “dynamic buckling.” Inspectors should
place emphasis on vehicle (dynamic) effects on track lateral stability, where
high rail temperatures and vehicle loading could progressively weaken the track
due to dynamic uplift (flexural waves) and a buckle mechanism response induced
by misalignment “growth.”
Because the majority of buckles occur under dynamic train
movements, loading is an important element in the buckling mechanism. Elements
of track lateral instability include:
• Formation of initial
track misalinement caused by reduced local resistance.
• High impact loads,
initial rail surface (weld) imperfections, “soft” spots in ballast, and
curve (radial breathing) shifting.
• Misalinement growth
caused by high lateral loads, increased longitudinal forces, track uplifts due
to vertical loads, and train-induced vibration.
Inspectors may consider the above elements, combined with
related evidence of actual defects, geometry conditions, or other defective
structural conditions, when evaluating the adequacy of a railroad’s CWR
stability procedures under §§ 213.119(b),
(c), (d), and
(e). Locations where
track buckling are more likely to occur include: horizontal and vertical curves,
bottom of grades, bridge approaches, highway-rail grade crossings,
recently-disturbed track, and areas of heavy train starting or braking.
The signs or precursors of buckles include:
• Newly formed alinement
deviations: wavy, kinky, snaky, etc.
• Rails rotating or lifting
out of the tie plates and intermittent loose tie plates.
• Excessive “running”
rail causing ties to plow or churn the ballast.
• Insufficient anchors and
anchors not installed tightly against the tie.
• Insufficient ballast
section in the crib and shoulder areas.
• Gaps at crosstie ends,
especially on the low (inner) rail.
Curves are more prone to buckling because of the curvature
effect, alinement imperfection sensitivity, and train loads. It is important for
inspectors to consider when and where a buckle may occur (e.g., on track
segments where the CWR installation occurred below the desired rail installation
temperature range and there was inadequate control of the laying temperature or
inadequate adjustment of the rail afterwards). In addition, inspectors should
observe areas of recent maintenance involving either the ballast or rail, where
there was inadequate reconsolidating time for a disturbed ballast or inadequate
temperature adjustment when replacing a defective rail. As curvature increases,
the buckling resistance decreases. Under some conditions, high degree curvature
can undergo gradual lateral shift (progressive buckling). Lateral alinement
deviations reduce the track buckling strength and can initiate growth to
critical levels. Vertical alinement deviations can also influence buckling.
Lateral misalinement is an important consideration because it
reduces the ability of the track to resist buckling. An alinement offset or
mid-ordinate within allowable limits may “escalate” under the imposed loads.
This is called “track shift.” A longitudinal force in curved track will
cause CWR rail to move radically. Compressive loads in the rail during the
summer tend to move the track outwards, and tensile loads in the winter will
pull the track inward, a term known as “radial breathing.” Inspectors should
review the allowable limits, under § 213.55, and evaluate the relevant
alinement and track strength (§ 213.13, Movement under load) due to repeated
thermal and vehicle loadings.
Generally speaking, a decrease in the rail neutral temperature
of 30–40 degrees from the installation temperature can be critical and lead
directly to buckling. Inspectors should monitor the following factors that may
influence shifts in the force-free temperature: improper rail installation,
inadequate rail anchors or fastenings, lateral movements in curves through
lining operations, “skeletonized” track segments (ballast removed for
maintenance purposes), and inadequate ballast section. Lateral and longitudinal
restraint is influenced by the factors mentioned above and, if improperly
maintained or allowed to exist in a defective state, it increases the opportunity for a track buckle.
Track buckles occur less frequently in tangent track than in
curves. However, buckling in tangent track will generally occur suddenly and
with more severe consequences.
The second of the two failure modes that can be associated with
track constructed with CWR is a pull-apart. A rail’s decrease in temperature
in the winter will create tensile forces. The maximum tensile load in the rail
is determined by the difference in the installation or force-free temperature
and the lowest rail temperatures. Enough tensile force can cause direct fracture
at rail cross-sections with prior cracks, weak welds, or sheared joint bolts at
CWR string end locations.
119(f) Procedures which govern train speed on CWR track when—
(1) Maintenance work, track rehabilitation, track construction,
or any other event occurs which disturbs the roadbed or ballast section and
reduces the lateral or longitudinal resistance of the track; and
(2) The difference between the average rail temperature and the
average rail neutral temperature is in a range that causes buckling-prone
conditions to be present at a specific location; and
Guidance: This requires
that the railroad needs to record the new rail neutral temperature when
performing rail repair and installation.
(3) In formulating the procedures under paragraphs (f)(1) and
(f)(2) of this section, the track owner shall—
(i) Determine the speed required, and the duration and
subsequent removal of any speed restriction based on the restoration of the
ballast, along with sufficient ballast re-consolidation to stabilize the track
to a level that can accommodate expected train-induced forces. Ballast
re-consolidation can be achieved through either the passage of train tonnage or
mechanical stabilization procedures, or both; and
(ii) Take into consideration the type of crossties used.
119(g) Procedures which prescribe when physical track
inspections are to be performed.
(1) At a minimum, these procedures shall address inspecting
track to identify—
(i) Buckling-prone conditions in CWR track, including—
(A) Locations where tight or kinky rail conditions are likely to
occur; and
(B) Locations where track work of the nature described in
paragraph (f)(1)(i) of this section has recently been performed; and
(ii) Pull-apart prone conditions in CWR track, including
locations where pull-apart or stripped-joint rail conditions are likely to
occur; and
(2) In formulating the procedures under paragraph (g)(1) of this
section, the track owner shall—
(i) Specify when the inspections will be conducted; and
(ii) Specify the appropriate remedial actions to be taken when
either buckling-prone or pull-apart prone conditions are found.
119(h) Procedures which prescribe the scheduling and conduct of
inspections to detect cracks and other indications of potential failures in CWR
joints. In formulating the procedures under this paragraph, the track owner
shall—
Guidance: This paragraph
requires each track owner to include in its CWR plan provisions for the
scheduling and conducting of joint inspections. A person who is qualified under
§ 213.7(c) will perform the inspections required by this paragraph on foot at
the joint.
(1) Address the inspection of joints and the track structure at
joints, including, at a minimum, periodic on-foot inspections.
Guidance: This paragraph
governs on-foot periodic inspections of CWR joints. Track owners are required to
establish procedures for conducting these inspections. Upon identifying actual
conditions of joint failures (i.e., broken or cracked joints bars) or potential
conditions of joint failure, track owners must initiate the appropriate
corrective action and keep the appropriate records. See § 213.119(h)(h)(5) and
§ 213.119(h)(7). In addition, when a track owner discovers CWR joints that are not
in compliance with the requirements of the TSS, the track owner must take the
appropriate remedial action required by Part 213. Inspectors should note that
nothing in this paragraph interferes with the track owners’ continuing
obligation to conduct track inspections under § 213.233. In addition, on-foot
periodic inspections can be performed concurrently with § 213.233.
Periodic inspections, as referenced herein, are on-foot
inspections of CWR joints that track owners must conduct on a regular basis.
Track owners are required to conduct on-foot periodic inspections at the minimum
intervals specified in paragraph (h)(6). Track owners, of course, are free to
conduct these inspections more frequently than required.
(2) Identify joint bars with visible or otherwise detectable
cracks and conduct remedial action pursuant to § 213.121;
Guidance: This paragraph
requires track owners to identify joint bars with visible or otherwise
detectable cracks and conduct remedial action pursuant to § 213.121. Railroad
inspectors must know to distinguish between joint bars that are already cracked
and joint bars that have the potential of cracking in the future. When a track
owner discovers a cracked joint bar, the owner must take any remedial action
specified in § 213.121; however, if the owner discovers a joint bar with actual
or potential joint failure, the owner must take the corrective action specified
by the CWR plan. Corrective action will be further addressed in paragraph
(h)(5).
(3) Specify the conditions of actual or potential joint failure
for which personnel must inspect, including, at a minimum, the following items:
(i) Loose, bent, or missing joint bolts;
(ii) Rail end batter or mismatch that contributes to instability
of the joint; and
(iii) Evidence of excessive longitudinal rail movement in or
near the joint, including, but not limited to; wide rail gap, defective joint
bolts, disturbed ballast, surface deviations, gap between tie plates and rail,
or displaced rail anchors;
Guidance: This paragraph
identifies those items relating to joint inspections that track owners must
address in their CWR plans. Inspectors should note that these items are the minimum that track owners should address. Of course, track
owners are free to include additional items in their respective CWR plans.
Railroad track inspectors are to identify and record action items listed during
their inspection of joints because these items are related to the integrity of
the joint, and thus, to the safety of trains that operate over these joints.
Inspectors should note that this list is not all-inclusive.
There are other conditions that could indicate failure, and inspectors should
urge track owners to consider all conditions, not just these listed examples.
(4) Specify the procedures for the inspection of CWR joints that
are imbedded in highway-rail crossings or in other structures that prevent a
complete inspection of the joint, including procedures for the removal from the
joint of loose material or other temporary material;
Guidance: This paragraph
requires track owners to include procedures in their CWR plans for the
inspection of CWR joints that are imbedded in highway-rail grade crossings or in
other structures that prevent a complete inspection of the joint (e.g., pans in
fueling facilities, scales, passenger walkways at stations that cover the track,
etc.). The plans must also include procedures for the removal of loose material
or other temporary material from the joint.
With respect to the procedures for “imbedded” joints,
inspectors should not expect railroads to disassemble or remove the track
structure (e.g., remove pavement or crossing pads) to conduct an inspection of
CWR joints. However, FRA expects that railroads will make every effort, to the
extent practicable, to inspect the joints in these structures.
Inspectors need to be aware that CWR joints may sometimes be
temporarily buried during maintenance (e.g., where ballast is distributed in the
middle of the track and along the track) and therefore unavailable for
inspection. FRA expects that railroads will take necessary measures to conduct
inspections of these CWR joints and expects that railroads will schedule their
maintenance to allow for a complete inspection of these joints. Where CWR joints
are buried (e.g., by ballast), inspectors should understand that railroad
maintenance personnel will wait for the completion of the track surfacing and
dressing of the ballast before conducting their joint bar inspections. However,
railroad employees may use hand tools or mechanical means to remove ballast from
the sides of track joints, so that they can conduct an inspection of those track
joints.
Finally, FRA notes that components of the track (such as
crossties, fasteners, tie plates, etc.) are also not fully visible in
highway-rail grade crossings and similar structures. Inspectors should note that
FRA has never specifically exempted these items from the inspections required
under Part 213. Inspectors should continue to expect that the railroads will
inspect these areas to the maximum extent possible.
(5) Specify the appropriate corrective actions to be taken when
personnel find conditions of actual or potential joint failure, including
on-foot follow-up inspections to monitor conditions of potential joint failure
in any period prior to completion of repairs;
Guidance: This paragraph
requires track owners to specify in their plans the appropriate corrective
actions that must be taken when track inspectors find conditions of actual or
potential joint failure. Inspectors should note the difference between the terms
“remedial actions” and “corrective action” and apply accordingly.
Remedial actions are those actions which track owners are required to take as a
result of requirements of Part 213 to address a noncompliant condition. For example, if a track owner discovers
a cracked joint bar, the owner must replace it. See § 213.121 or the parallel
requirement in the railroad’s CWR plan. Corrective actions, on the other hand,
are those actions that track owners specify in their CWR plans to address
conditions of potential joint failure, including, as applicable, repair,
restrictions on operations, and/or additional on-foot inspection. To ensure
clarity, FRA has defined these terms in § 213.119(j).
On-foot followup inspections, as referenced herein, are
joint-specific and conducted in response to conditions that a track owner
discovers during periodic inspections. Track owners will identify in their CWR
plans the conditions that trigger followup inspections. For example, where a
track owner identifies “replace bolt or inspect weekly” as a corrective
action for a bent bolt, if a track inspector discovers a bent bolt during a
periodic inspection and does not immediately replace it, then the track
inspector will have to conduct followup inspections at that joint at the
specified frequency (in this case, weekly).
(6) Specify the timing of periodic inspections, which shall be
based on the configuration and condition of the joint:
Guidance: This paragraph
requires railroad owners to specify the timing of on-foot periodic inspections.
The minimum number of required joint inspections is addressed in the table in
paragraph (h)(6)(i). The timing periods in this paragraph represent the minimum
of what is expected. Railroad owners are encouraged to implement additional
inspection periods as they determine necessary.
In paragraphs (h)(6)(ii) through (iv), inspectors should be
aware that FRA is allowing exceptions to the minimum inspection frequencies for
unscheduled detours, certain passenger trains, and items that are already
inspected on a monthly basis pursuant to § 213.235. Each of these exceptions
will be discussed in more detail below.
(i) Except as provided in paragraphs (h)(6)(ii) through
(h)(6)(iv) of this section, track owners must specify that all CWR joints are
inspected, at a minimum, in accordance with the intervals identified in the
following table:
[1] Where a track owner operates both freight and passenger
trains over a given segment of track, and there are two different possible
inspection interval requirements, the more frequent inspection interval applies.
[2] When extreme weather conditions prevent a track owner from
conducting an inspection of a particular territory within the required interval,
the track owner may extend the interval by up to 30 calendar days from the last
day that the extreme weather condition prevented the required inspection
Guidance: The first
footnote provides that where a track owner operates both freight and passenger
trains over a given segment of track, and there are two different possible
inspection interval requirements, the more frequent inspection interval applies.
This footnote was developed to address concerns over track shared by freight and
passenger trains. It was anticipated that there could be a potential conflict
with the inspection frequency required for the track if the track owner were to
follow the chart for both types of trains. By requiring the more frequent
inspections in situations of conflict, this footnote ensures greater safety and
protection to track used for mixed purposes.
The second footnote was added in response to concerns regarding
sensitivity of extreme regional weather conditions. Concern was raised with
regard to the difficulty of inspecting CWR joints in northern regions when there
is a large amount of snow. FRA notes that there could be times when it would be
extremely difficult for a track owner to clear snow and ice from the joint in
order for it to be seen for inspection. This footnote allows some flexibility
for track owners in such a situation.
(ii) Consistent with any limitations applied by the track owner,
a passenger train conducting an unscheduled detour operation may proceed over
track not normally used for passenger operations at a speed not to exceed the
maximum authorized speed otherwise allowed, even though CWR joints have not been
inspected in accordance with the frequency identified in paragraph (h)(6)(i) of
this section, provided that:
(A) All CWR joints have been inspected consistent with
requirements for freight service; and
(B) The unscheduled detour operation lasts no more than 14
consecutive calendar days. In order to continue operations beyond the 14-day
period, the track owner must inspect the CWR joints in accordance with the
requirements of paragraph (h)(6)(i) of this section.
Guidance: This paragraph
allows track owners, for a limited period of time, to operate passenger trains
without lowering the track speed and without adhering to the required inspection
frequencies for passenger trains pursuant to the table in § 213.119(h)(6)(i).
This provision accommodates for unplanned outages, derailments, accidents, and
other emergency situations. Track owners are still required to adhere
to the applicable freight inspection frequencies. This provision is intended to
provide relief to railroads that operate passenger trains and that have a
last-minute emergency situation. However, if a track owner operates passenger
trains at the normal track speed for more than 14 days, the track must be
inspected at the appropriate passenger train levels, as detailed in the chart at
§ 213.119(h)(6)(i).
(iii) Tourist, scenic, historic, or excursion operations, if
limited to the maximum authorized speed for passenger trains over the next lower
class of track, need not be considered in determining the frequency of
inspections under paragraph (h)(6)(i) of this section.
Guidance: As defined in
§ 213.119(l), tourist, scenic, historic, or excursion operations are railroad
operations that carry passengers with the conveyance of the passengers to a
particular destination not being the principal purpose. These operations run
less frequently than intercity or commuter passenger trains, and occur most
often on shortline railroads. If a track owner has an operation of this type on
the track and does not want to take that operation into account in determining
inspection frequency, the owner must drop the track speed one class with regard
to that operation. This way, the track owner will be still be in compliance with
the inspection frequency mandated by the table in paragraph (h)(6)(i),
regardless of the class of freight the owner runs on the track. As the first
footnote to the table in paragraph (h)(6)(i) states, where there are two
different possible inspection interval requirements, the more frequent
inspection interval applies.
The above is a consideration for situations where tourist trains
operate on the general system of transportation. For tourist trains on track
other than the general system of transportation, such operations are normally
not subject to the TSS. See Part 209, Appendix A.
(iv) All CWR joints that are located in switches, turnouts,
track crossings, lift rail assemblies or other transition devices on moveable
bridges must be inspected on foot at least monthly, consistent with the
requirements in § 213.235; and all records of those inspections must be kept in
accordance with the requirements in § 213.241. A track owner may include in its
§ 213.235 inspections, in lieu of the joint inspections required by paragraph
(h)(6)(i) of this section, CWR joints that are located in track structure that
is adjacent to switches and turnouts, provided that the track owner precisely
defines the parameters of that arrangement in the CWR plans.
Guidance: This paragraph
exempts the following items from the periodic inspection frequency intervals:
switches, turnouts, track crossings, lift rail assemblies, or other transition
devices on moveable bridges. Track owners already inspect these items on a
monthly basis pursuant to § 213.235. Rather than apply the additional periodic
inspection requirements (i.e., apply the intervals in the table in §
213.119(h)(6)(i) to switches and turnouts, etc.), FRA believes it is more
appropriate to have track owners conduct their inspections of joints at these
locations during their monthly § 213.235 inspections.
FRA has historically understood and operated under the
assumption that a turnout extends from the point of the switch to the heel of
the frog. Inspectors should continue to operate under that assumption, and
accordingly, all joints in turnouts, switches, etc. must be inspected monthly,
pursuant to § 213.235, and records of these inspections must be kept in
accordance with § 213.241. The regulation does not require that the data
elements listed in § 213.119(h)(7)(i) appear on the § 213.235 inspection
record.
All joints that extend beyond the point of a switch or beyond
the heel of the frog must be inspected at the frequency intervals identified in
§ 213.119(h)(6)(i). However, track owners are free to include, in their monthly
§ 213.235 inspection, these joints that are located in track structure that is
adjacent to turnouts and switches. If track owners choose to do this, they must
clearly define the parameters of that arrangement in their CWR plan. In other
words, the track owner should clearly identify the physical limits of the
adjacent track structure (e.g., insulated joints up until the signal), and they
must clearly identify the inspection interval for joints in that adjacent track
(e.g., “inspect all insulated joints to the signal during the monthly §
213.235 inspection”).
In addition, as long as track owners clearly define the
parameters in the CWR plans, the track owner does not need to keep two sets of
records (e.g., a record from the § 213.235 inspection and a record from the §
213.119(h)(6)(i) inspection) for inspections of these “adjacent” joints. For
example, if the track owner’s CWR plan indicates that joints in crossovers
between turnouts must be inspected during the monthly § 213.235 inspection, and
a railroad track inspector inspects the joints in the crossover during the
monthly § 213.235 inspection, then it is sufficient for the track owner to
create and maintain only the § 213.235 record.
FRA believes this option is useful because it avoids the
confusion and duplication that might otherwise result. In addition, FRA notes
that it would be burdensome for track inspectors to inspect those “adjacent”
joints monthly and make a note of the inspection in the monthly § 213.235
record, and also be required to make an additional § 213.119(h)(6)(i) record
every few months.
(7) Specify the recordkeeping requirements related to joint bars
in CWR, including the following:
(i) The track owner shall keep a record of each periodic and
follow-up inspection required to be performed by the track owner’s CWR plan,
except for those inspections conducted pursuant to § 213.235 for which track
owners must maintain records pursuant to § 213.241. The record shall be
prepared on the day the inspection is made and signed by the person making the
inspection. The record shall include, at a minimum, the following items: the
boundaries of the territory inspected; the nature and location of any deviations
at the joint from the requirements of this part or of the track owner’s CWR
plan, with the location identified with sufficient precision that personnel
could return to the joint and identify it without ambiguity; the date of the
inspection; theremedial action, corrective action, or both, that has been taken
or will be taken; and the name or identification number of the person who made
the inspection.
Guidance: This paragraph
addresses the inspection reports that have to be created after periodic
inspections required by paragraph (h)(6)(i), and followup inspections as
required by the track owner’s CWR plan. The inspection reports of the periodic
inspections shall be prepared on the day the inspection is made and are to
contain the required information. The periodic inspection record can be combined
with other records required pursuant to § 213.241.
(ii) The track owner shall generate a Fracture Report for every
cracked or broken CWR joint bar that the track owner discovers during the course
of an inspection conducted pursuant to §§ 213.119(g),
213.233, or 213.235 on
track that is required under § 213.119(h)(6)(i) to be inspected.
(A) The Fracture Report shall be prepared on
the day the cracked or broken joint bar is discovered. The Report shall include,
at a minimum: the railroad name; the location of the joint bar as identified by
milepost and subdivision; the class of track; annual million gross tons for the
previous calendar year; the date of discovery of the crack or break; the rail
section; the type of bar (standard, insulated, or compromise); the number of
holes in the joint bar; a general description of the location of the crack or
break in bar; the visible length of the crack in inches; the gap measurement
between rail ends; the amount and length of rail end batter or ramp on each rail
end; the amount of tread mismatch; the vertical movement of joint; and in curves
or spirals, the amount of gage mismatch and the lateral movement of the joint.
(B) The track owner shall submit the
information contained in the Fracture Reports to the FRA Associate Administrator
twice annually, by July 31 for the preceding six-month period from January 1
through June 30 and by January 31 for the preceding six-month period from July 1
through December 31.
(C) After February 1, 2010, any track owner
may petition FRA to conduct a technical conference to review the Fracture Report
data submitted through December of 2009 and assess whether there is a continued
need for the collection of Fracture Report data. The track owner shall submit a
written request to the Associate Administrator, requesting the technical
conference and explaining the reasons for proposing to discontinue the
collection of the data.
Guidance: This
paragraph requires railroads to generate Fracture Reports that are also required
to be submitted to the Associate Administrator twice annually, pursuant to §
213.119(h)(7)(ii)(B). Railroads must complete Fracture Reports when they find
cracks or breaks during routine inspections pursuant to §§ 213.119(g),
213.233, or 213.235, on track that is required to be inspected under §
213.119(h)(6)(i). FRA intends to use the Fracture Reports to collect CWR rail
joint data; FRA does not intend to use the Fracture Reports for enforcement
purposes. Inadvertent errors on Fracture Reports submitted by railroads
employees should not be subject to civil penalties. Although, pursuant to §
213.119(h)(6)(i), track owners are not required to complete a Fracture Report
for cracks or breaks found in excepted track, Class 1 track, and Class 2 track
without passenger service, inspectors should encourage track owners to complete
Fracture Reports whenever cracks or breaks are discovered, in addition to the
required inspections.
If an FRA inspector encounters repeated failure to prepare and complete
reports or comes upon a persistent and recurring pattern of non-reporting,
inspectors are to inform their regional specialist of the non-reporting. The
regional specialist will confer with Division staff to determine appropriate
enforcement action. Track owners are not required to keep the Fracture Reports
pursuant to the requirements of § 213.241. However, Fracture Reports should be
kept until the track owner has received confirmation from headquarters that the
data has been received.
FRA has provided four options as a means for the track owner to submit
Fracture Reports. The first option is through an electronic data submission
using Extensible Markup Language (XML) format. This option allows the railroad
to decide how best to capture the information, yet still submit it to FRA in a
standard and valid way. The railroads can submit the information Track
and Rail and Infrastructure Integrity Compliance Manual Volume II, Chapter 1 –
January 2014 2.1.94
to FRA by sending the XML files directly to FRA via email. The second option,
the fillable PDF format, uses a fillable Adobe PDF file to capture and submit
the data. The railroad can complete each report and submit the Adobe-generated
XML file to FRA via a submit button located on the form. Third, FRA has made
available a formatted Excel spreadsheet, into which railroads can input their
Fracture Reports. This spreadsheet can be submitted via email, electronic media,
or uploaded to the FRA Office of Safety Analysis’ Web site. As a final option,
FRA has made a printable version of the OMB-approved Fracture Report form
available for download. See Appendix E to this compliance manual for an
unofficial copy of the form; however, railroads wishing to submit the form in
hard copy should use the fracture report form that is available for download,
rather than this unofficial copy. More specific instructions regarding
submission of the report are available on the Office of Safety Analysis’ Web
site at the following address: http://safetydata.fra.dot.gov/CWR/.
Paragraph (A) requires that the Fracture Report be prepared on the day the
cracked or broken CWR joint bar is found. The Fracture Report is to be completed
whenever a cracked or broken joint bar is discovered during the periodic
inspections required by § 213.119(h)(6)(i), as well as those currently required
by §§ 213.233 and 213.235.
The annual million gross tonnage information requested in the Fracture Report
can be entered on the report by another designated employee of the railroad,
since the railroad track inspector may not have ready access to this
information. However, the inspector should be made aware of the range within
which the value falls as a result of instructions provided concerning the
frequency of inspection required.
Paragraph (B) requires the track owner to submit the information contained in
the Fracture Reports twice annually to FRA. FRA is collecting the Fracture
Report data and will review and analyze it to better determine the root causes
of joint failures.
In addition, FRA inspectors will be expected to submit Fracture Reports when
cracked or broken CWR joint bars are found during an inspection that are a
defect or an exception to the railroad’s CWR plan, in addition to noting the
defect on their report. However, only one Fracture Report is to be submitted for
a defective joint. An FRA inspection is not one of the required times that a
railroad must submit a Fracture Report. However, the railroad may voluntarily
complete the form; therefore, the FRA inspector would not complete and submit
the form. Inspectors are to complete their reports on the fillable PDF form,
which can be found on the FRA’s Office of Safety Analysis Web site under the
"CWR" toolbar tab. The submit button will email the Adobe-generated
XML file to a predetermined address.
Paragraph (C) allows any track owner to petition FRA after February 1, 2010,
to conduct a technical conference to assess whether there is a continued need
for the collection of Fracture Report data. During the technical conference, FRA
would review the data collected and the analysis done to date, and determine if
sufficient data has been collected to enable FRA to make a technically competent
determination of CWR joint bar failure causes and contributing conditions.
(8)
In lieu of the requirements for the inspection of rail joints contained in
paragraphs (h)(1) through (h)(7) of this section, a track owner may seek
approval from FRA to use alternate procedures.
(i) The track owner shall submit the
proposed alternate procedures and a supporting statement of justification to the
Associate Administrator.
(ii) If the Associate Administrator finds that
the proposed alternate procedures provide an equivalent or higher level of
safety than the requirements in paragraphs (h)(1) through (h)(7) of this
section, the Associate Administrator will approve the alternate procedures by
notifying the track owner in writing. The Associate Administrator will specify
in the written notification the date on which the procedures will become
effective, and after that date, the track owner shall comply with the
procedures. If the Associate Administrator determines that the alternate
procedures do not provide an equivalent level of safety, the Associate
Administrator will disapprove the alternate procedures in writing, and the track
owner shall continue to comply with the requirements in paragraphs (h)(1)
through (h)(7) of this section.
(iii) While a determination is pending with
the Associate Administrator on a request submitted pursuant to paragraph (h)(8)
of this section, the track owner shall continue to comply with the requirements
contained in paragraphs (h)(1) through(h)(7) of this section.
Guidance: This
paragraph permits a track owner to devise an alternate program for the
inspection of joints in CWR. A track owner seeking to deviate from the minimum
inspection frequencies specified in § 213.119(h)(6) should submit the alternate
procedures and a supporting statement of justification to FRA’s Associate
Administrator for Railroad Safety/Chief Safety Officer. In the supporting
statement, the track owner must include data and analysis that establishes (to
the satisfaction of the Associate Administrator for Railroad Safety/Chief Safety
Officer) that the alternate procedures provide at least an equivalent level of
safety across the railroad.
If the Associate Administrator for Railroad Safety/Chief Safety Officer
approves the alternate procedures, the Associate Administrator for Railroad
Safety/Chief Safety Officer will notify the track owner of such approval in
writing. In that written notification, the Associate Administrator for Railroad
Safety/Chief Safety Officer will specify the date that the alternate procedures
will become effective. After that date, the track owner shall comply with the
approved procedures. If the Associate Administrator for Railroad Safety/Chief
Safety Officer determines that the alternate procedures do not provide an
equivalent level of safety, the Associate Administrator for Railroad
Safety/Chief Safety Officer will disapprove the alternate procedures in writing.
While a determination is pending with the Associate Administrator for Railroad
Safety/Chief Safety Officer, the track owner shall continue to comply with the
requirements contained in § 213.119(h)(6).
Technology (including frequent automated track geometry surveys) and sound
CWR management, including prompt removal of "temporary" joints, may
provide the additional information required to verify the ongoing integrity of
joints in CWR. The alternative procedures provision of this final rule will
allow track owners to take advantage of these new approaches as they become
available.
(i) The track owner shall submit the proposed alternate
procedures and a supporting statement of justification to the Associate
Administrator.
(ii) If the Associate Administrator finds that the proposed
alternate procedures provide an equivalent or higher level of safety than the
requirements in paragraphs (h)(1) through (h)(7) of this section, the Associate
Administrator will approve the alternate procedures by notifying the track owner
in writing. The Associate Administrator will specify in the written notification
the date on which the procedures will become effective, and after that date, the
track owner shall comply with the procedures. If the Associate Administrator
determines that the alternate procedures do not provide an equivalent level of
safety, the Associate Administrator will disapprove the alternate procedures in
writing, and the track owner shall continue to comply with the requirements in
paragraphs (h)(1) through (h)(7) of this section.
(iii) While a determination is pending with the Associate
Administrator on a request submitted pursuant to paragraph (h)(8) of this
section, the track owner shall continue to comply with the requirements
contained in paragraphs (h)(1) through(h)(7) of this section.
119(i)
The track owner shall have in effect a comprehensive
training program for the application of these written CWR procedures, with
provisions for annual re-training, for those individuals designated under §
213.7(c) as qualified to supervise the installation, adjustment, and maintenance
of CWR track and to perform inspections of CWR track. The track owner shall make
the training program available for review by FRA upon request.
Guidance: All railroad
employees designated under § 213.7(c) as qualified to supervise the
installation, adjustment, and maintenance of CWR track and to perform
inspections of CWR track must be trained on the track owner’s CWR plan. The
track owner shall maintain a written record of this training in accordance with
§ 213.7(e). Inspectors should refer any requests for training programs to their
regional office. Railroad representatives agree to voluntarily make an initial
submission of their CWR training programs to FRA. Track inspectors should not
request the training program of a specific track owner unless under the specific
direction of FRA management. Rather, FRA headquarters staff will undertake the
responsibility of obtaining and disseminating this information, as needed, to
both FRA inspectors and State inspectors participating in rail safety
enforcement activities under Title 49 Code of Federal Regulations (CFR) Part
212. However, inspectors can request a copy of the track owner’s qualification
list during regular business hours.
119(j) The track owner shall prescribe and comply with
recordkeeping requirements necessary to provide an adequate history of track
constructed with CWR. At a minimum, these records must include:
(1) Rail temperature, location, and date of CWR installations.
Each record shall be retained for at least one year;
(2) A record of any CWR installation or maintenance work that
does not conform to the written procedures. Such record shall include the
location of the rail and be maintained until the CWR is brought into conformance
with such procedures; and
(3) Information on inspection of rail joints as specified in
paragraph (h)(7) of this section.
Guidance: Paragraph (j)
contains the recordkeeping requirements for railroads that have track
constructed of CWR. At a minimum, a track owner must keep records of the items
listed in paragraphs (j)(1) through (j)(3). Paragraph (j)(1) requires each
railroad to keep a record of the rail temperature, location, and date of the CWR
installations. Paragraph (j)(2) requires a track owner to keep a record of any
CWR installation or maintenance work that does not conform with the written
procedures. Also, (f)(2) requires the railroad to determine the difference
between the average rail temperature and the average rail neutral temperature.
This necessitates the recording of rail neutral temperatures at rail repair
locations that do not conform to the procedures. Paragraph (j)(3) requires a
track owner to keep records of information on inspection of rail joints as
specified in paragraph (h)(7).
119(k) The track owner shall make readily available, at every
job site where personnel are assigned to install, inspect or maintain CWR, a
copy of the track owner’s CWR procedures and all revisions, appendices,
updates, and referenced materials related thereto prior to their effective date.
Such CWR procedures shall be issued and maintained in one CWR standards and
procedures manual.
Guidance: Since the
implementation of the CWR regulations, FRA has noted that a number of rail
carriers maintain two different sets of CWR procedures. Additionally, some
railroads have been maintaining the set of CWR procedures submitted to FRA as
required by this section (§ 213.119), as well as a separate set of CWR
procedures that is used by personnel in the field. While it may be acceptable
for a railroad to instruct its personnel to maintain more restrictive CWR
procedures in the field than what is on file with FRA, it is important to note
that railroads must train their personnel on the plan formally submitted and
filed with FRA. As FRA enforces the track owner’s CWR plan on file with its
Office of Railroad Safety, it is critical to have these procedures at every job
site where personnel are assigned to install, inspect, or maintain CWR.
Specifically, this will ensure that personnel in the field understand which set
of procedures FRA will hold them responsible for compliance with the TSS.
119(l) As used in this section—
Adjusting/de-stressing means the procedure by which a rail’s
temperature is re-adjusted to the desired value. It typically consists of
cutting the rail and removing rail anchoring devices, which provides for the
necessary expansion and contraction, and then re-assembling the track.
Annual re-training means training every calendar year.
Buckling incident means the formation of a lateral misalignment
sufficient in magnitude to constitute a deviation from the Class 1 requirements
specified in § 213.55. These normally occur when rail temperatures are
relatively high and are caused by high longitudinal compressive forces.
Buckling-prone condition means a track condition that can result
in the track being laterally displaced due to high compressive forces caused by
critical rail temperature combined with insufficient track strength and/or train
dynamics.
Continuous welded rail (CWR) means rail that has been welded
together into lengths exceeding 400 feet. Rail installed as CWR remains CWR,
regardless of whether a joint or plug is installed into the rail at a later
time.
Corrective Actions mean those actions which track owners specify
in their CWR plans to address conditions of actual or potential joint failure,
including, as applicable, repair, restrictions on operations, and additional
on-foot inspections.[1]
CWR joint means any joint directly connected to
CWR.
Desired rail installation temperature range means the rail
temperature range, within a specific geographical area, at which forces in CWR
should not cause a buckling incident in extreme heat, or a pull-apart during
extreme cold weather.
Disturbed Track means the disturbance of the roadbed or ballast
section, as a result of track maintenance or any other event, which reduces the
lateral or longitudinal resistance of the track, or both.
Mechanical stabilization means a type of procedure used to
restore track resistance to disturbed track following certain maintenance
operations. This procedure may incorporate dynamic track stabilizers or ballast
consolidators, which are units of work equipment that are used as a substitute
for the stabilization action provided by the passage of tonnage trains.
Pull apart or stripped joint means a condition when no bolts are
mounted through a joint on the rail end, rending the joint bar ineffective due
to excessive expansive or contractive forces.
Pull-apart prone condition means a condition when the actual
rail temperature is below the rail neutral temperature at or near a joint where
longitudinal tensile forces may affect the fastenings at the joint.
Rail anchors means those devices which are attached to the rail
and bear against the side of the crosstie to control longitudinal rail movement.
Certain types of rail fasteners also act as rail anchors and control
longitudinal rail movement by exerting a downward clamping force on the upper
surface of the rail base.
1 Note,
this term is used in § 213.119(h)(5).
Rail neutral temperature is the temperature at which the rail is
neither in compression nor tension.
Rail temperature means the temperature of the rail, measured
with a rail thermometer.
Remedial Actions mean those actions which track owners are
required to take as a result of requirements of this part to address a
non-compliant condition.
Tight/kinky rail means CWR which exhibits minute alinement
irregularities which indicate that the rail is in a considerable amount of
compression.
Tourist, scenic, historic, or excursion operations mean railroad
operations that carry passengers with the conveyance of the passengers to a
particular destination not being the principal purpose.
Track lateral resistance means the resistance provided by the
rail/crosstie structure against lateral displacement.
Track longitudinal resistance means the resistance provided by
the rail anchors/rail fasteners and the ballast section to the rail/crosstie
structure against longitudinal displacement.
Train-induced forces means the
vertical, longitudinal, and lateral dynamic forces which are generated during
train movement and which can contribute to the buckling potential of the rail.
Unscheduled detour operation means a short-term, unscheduled
operation where a track owner has no more than 14 calendar days’ notice that
the operation is going to occur.
121(a) Each rail joint, insulated joint, and compromise joint
shall be of a structurally sound design and dimensions for the rail on which it
is applied.
Guidance: For
proper rail load transfer to occur, rail joints must contact the head and base
of the rails when the bolts are tight. Many rail joint designs have been used
with varying degrees of success, and the TSS does not attempt to single out any
particular design as the only acceptable joint. This could inhibit innovation in
modern track design.
The TSS requires structural soundness and bolt condition based on maximum
authorized train speed. Inspectors must be attentive to locations where standard
joint bars are used to join dissimilar rail sections where it would be proper to
have compromise bars.
The TSS recognize these important aspects of rail joints and begin this
section with a requirement that rail joints have a structurally sound design and
dimension for the rail on which they are applied.
Rail joints are considered to be a necessary discontinuity and require
special attention by railroad maintenance personnel, railroad inspectors, and
FRA inspectors. As far as possible, a rail joint should provide the same
relative strength, stiffness, flexibility, and uniformity as the rail itself.
The following figure illustrates the proper application of compromise joint bars
As shown in the following figure, one of the design
elements of joint bars to consider is if it’s a head-contact or head-free
design:
• The head-contact bar supports the rail ends with a
box-type construction, carrying the load between the underside of the head and
the base of the rail.
• The head-free joint bar does not contact the
underside of the rail heads, but instead contacts the rail in the fillet area.
The load distribution is referred to as a triangular load distribution
The use of a standard (noncompromise) joint bar of head-contact design on
a rail section other than for designed may constitute a deviation. The
differences between the head-contact joint bar and the head-free joint bar are
significant.
It is evident the joint bar and the rails do not bend or flex exactly with
each other along their length. Tests and measurements show that for positive
bending, there exists a downward bearing pressure of the under side of the head
of the rail on the top surface of the joint bars for some distance along the bar
away from the rail ends, (approximately 2 inches). There is also an upward
bearing pressure of the upper surface of the base of the rails at parts of the
length of the bar further away from the rail end, (bearing distance
approximately 3 inches). The converse is true for negative bending.
The head-free joint bar accepts bearing and shear forces from vertical
loads in the rail’s upper fillet. A head-contact bar is not designed to fit
into the filet. Specifically, the head-contact joint bar accepts bearing from
vertical loads on the flat underside of the rail’s head: generally on a 1 to 4
slope. It is not designed to seat into the rail’s upper filet. Although the
vertical fishing dimension for the 112 and 115 RE rail sections is identical (33/16
inches), the head filet radius is different:
• For the 115-pound section, radius equals three-fourths of an inch
• For the 112-pound section, radius equals three-eighths of an inch
As shown in the following figure, the 115 head-free bar fits the 112 rail
filet practically at a point, most probably inducing joint bar stresses in
excess of design which is a deviation from § 213.121(a). The 112 head-contact
bar does properly not fit into the 115 rail fillet as it bears in very small
areas beneath the head of the rail, possibly inducing joint bar stresses in
excess of design and exerting a wedge action between the rail head and rail web,
promoting head and web separation. In addition, the joint bar may experience a
twist, or torsional force from the tightening of the track bolts when used as a
compromise between 115 and 112 rail. The torsional stress from twist will be the
greatest at the head and toe of the bar at the rail ends.
There are exceptions to the use of a joint bar of head-contact design on a
rail section other than for designed. For example, a 131-pound or 132-pound
head-contact joint bar may be used in lieu of a 131/132 or 131/136 compromise
joint bar if rail drilling and joint bar punching is the same. The width of the
rail head in these configurations is sufficient to allow full contact in the
upper fishing wear surface. In summary:
• 112-pound RE joint bars should not be used as compromise joint bars
between 112 RE and 115 RE rail.
• 115-pound RE joint bars should not be used as compromise joint bars
between 112 RE and 115 RE rail.
• 131 RE head-contact bars or 132 RE head-contact bars may be used as
compromise joint bars between 131 RE and 132 RE rail or 136 RE rail where rail
drilling and joint bar punching are the same. (Note: FRA Standards do not
prohibit the track owner from field drilling bolt holes to fit).
While the above addresses compromise joint
bars, it is stressed that 112 RE bars are not to be used on 115 RE and 119 RE
rail and vice versa. Joint bars with 131 RE head-free and 132 RE head-free
design, or 131 RE head-free and 136 RE head-free joint bars, are not
interchangeable and are not to be intermixed.
For a compendium of rail section dimensions in order to compare other rail
sections for compatibility between joint bars on various rail sections refer to
Appendix C of this manual.
121(b) If a joint bar on Classes 3 through 5 track is cracked,
broken, or because of wear allows excessive vertical movement of either rail
when all bolts are tight, it shall be replaced.
Guidance: Joint
bars are designed to fit into the space between the bottom of the rail head and
rail base (fishing). With the bolts tight, the joint bars are wedged into the
fishing space to provide lateral and vertical beam strength thereby supporting
the abutting rail ends. When held up against the rail with bolts, joint bars
contact the rail at two points; bottom of the rail head (or fillet) and top of
the rail base. These contact points, known as the "fishing surfaces,"
can experience metal loss due to abrasion and mechanical wear that occurs during
the cyclical train dynamic loading. After long-term service, the fishing
surfaces of the rails and bars can wear to the point that joint bars are no
longer wedged into the rail, even with tight bolts. In such cases, the joint
assembly will no longer optimally support the abutting rail ends.
Joints with minimally worn fishing surfaces can provide for the safe passage
of wheels in Classes 1 through 5. As a guide, excessive vertical movement would
exist when there is significant fishing surface wear and wheel loads cause the
abutting rail ends to exhibit tread mismatch approaching the thresholds under §
213.115. If excessive vertical movement occurs, or there are any cracks,
corrective action would be to replace the bars or take other proper corrective
action.
Proper corrective action for a joint bar cracked or broken, other than center
break, in Classes 3 through 5 track, would be replacement or a reduction to
Class 2. If both joint bars are cracked or broken between the 1st and 2nd bolt
hole (including through the 2nd bolt hole), it should be considered Class 1.
This is because there is only one bolt in a rail end that is within the
remaining section of the joint bar that is providing support.
121(c) If a joint bar is cracked or broken between the middle
two bolt holes it shall be replaced.
Guidance: For
a center cracked or broken bar, the appropriate corrective action would be
replacement or reduction to Class 1 speeds under the provisions of § 213.9(b).
121(d)
In the case of conventional jointed track, each rail
shall be bolted with at least two bolts at each joint in Classes 2 through 5
track, and with at least one bolt in Class 1 track.
Guidance: Track
owners must have the number of required bolts in each rail in a joint. This
paragraph does not prescribe a tightness (torque) standard for each bolt. A bolt
that no longer can support the joint bar against the rail will continue to
provide resistance to pull aparts when the rail is in tension. The ability of
the bolts to hold bars against the rail to support the abutting rail ends is
covered under § 213.121(f).
A bolt does not fulfill the requirements of this paragraph if it is in
imminent danger of complete failure (it no longer is holding the bar to the rail
and no longer resists pull apart forces). For example, the nut is missing (it
will likely fall out under subsequent train movements) or the bolt shaft is
fractured.
121(e) In the case of continuous welded rail track, each rail
shall be bolted with at least two bolts at each joint.
Guidance: Rail
installed as CWR remains as CWR, regardless of whether a joint or plug is
installed at a later time. If there is only one bolt in a rail end at a joint,
in a CWR string, that one bolt will be subject to all the tensile axial forces
and will easily shear (break) resulting in a pull-apart.
121(f)
Each
joint bar shall be held in position by track bolts tightened to allow the joint
bar to firmly support the abutting rail ends and to allow longitudinal movement
of the rail in the joint to accommodate expansion and contraction due to
temperature variations. When no-slip, joint-to-rail contact exists by design,
the requirements of this paragraph do not apply. Those locations when over
400-feet in length, are considered to be continuous welded rail track and shall
meet all the requirements for continuous welded rail track prescribed in this
part.
Guidance: If the joint bars are loose, the joint is not in compliance with
§ 213.121(f). In addition, a joint assembly is not in compliance when
inadequately tightened bolts prevent it from supporting the abutting rail ends
under the expected traffic loads.
Joint bolts can deteriorate sufficiently as to create a condition where
the bars may become completely detached from the rail or cause a total lack of
support, which can contribute to a broken rail. Such a condition can create a
mismatch which exceeds the limits specified in § 213.115 (Rail end mismatch).
In such a case, the defect would be rail end mismatch (class specific) and
inspectors should also include a notation about the loose joint bars.
This paragraph also recognizes the design characteristic that enables the
rail ends in a joint to move longitudinally to handle temperature changes
(expansion/contraction) or rail creep (traffic flow). This type of joint bar
assembly is standard for jointed rail because that type of track construction
has lower axial forces than CWR. In CWR, it is desirable to contain the rail
expansion and contraction in the remaining joints (i.e., insulated joints) in
order to eliminate the pull-apart action that occurs in regular joints. In CWR,
the track structure, by design, dissipates the axial forces. Accordingly, this
paragraph allows joint designs that stop the axial rail movement within the
assembly.
Except for the axial movement component of this paragraph, joint bars such
as glued insulated joints are subject to all of the remaining requirements of
this paragraph and all other paragraphs of § 213.121. These types of assemblies
are considered to be joints, even in CWR (see § 213.119). However, for the
definition as to what constitutes CWR, a glued joint is not a longitudinal
discontinuity in a rail string. Glued joints are also considered joints under §
213.109 with respect to the required positioning of nondefective ties at joints.
121(g)
No rail shall have a bolt hole which is torch cut or
burned in Classes 2 through 5 track.
Guidance. This paragraph
prohibits the use of a rail containing a bolt hole that has been torch cut or
burned in Classes 2 through 5 track.
121(h) No joint bar shall be reconfigured by torch cutting in
Classes 3 through 5 track.
Guidance. This paragraph
prohibits the reconfiguration of joint bars by torch cutting in Classes 3
through 5 track. By omission of the reference to Classes 1 and 2 track, this
practice of reconfiguration is allowed in those classes. However, the joint bars
that are reconfigured by torch cutting must meet certain criteria for structural
soundness of design and dimension, which is required under (a) of this section.
122(a) Except as a temporary repair in emergency situations no
rail having a torch cut end shall be used in Classes 3 through 5 track. When a
rail end is torch cut in emergency situations, train speed over that rail end
shall not exceed the maximum allowable for Class 2 track. For existing torch cut
rail ends in Classes 3 through 5 track the following shall apply –
(1) Within one year of September 21, 1998, all torch cut rail
ends in Class 5 track shall be removed;
(2) Within two years of September 21, 1998, all torch cut rail
ends in Class 4 track shall be removed; and
(3) Within one year of September 21, 1998, all torch cut rail
ends in Class 3 track over which regularly scheduled passenger trains operate,
shall be inventoried by the track owner.
Guidance. The regulation
prohibits the torch cutting of rail ends in Classes 3 through 5 track except as
a temporary repair in emergency situations. In such emergency situations, train
speed shall not exceed the maximum allowable for Class 2 track.
Existing torch cuts must be removed from track in the following
time frames:
• Class 5 track – by
September 21, 1999.
• Class 4 track – by
September 21, 2000.
• Class 3 track with
passenger trains – by September 21, 1999, all torch cuts shall be inventoried
by the track owner.
122(b) Following the expiration of the time limits specified in
(a)(1), (2), and (3) of this section, any torch cut rail end not removed from
Classes 4 and 5 track, or any torch cut rail end not inventoried in Class 3
track over which regularly scheduled passenger trains operate, shall be removed
within 30 days of discovery. Train speed over that rail end shall not exceed the
maximum allowable for Class 2 track until removed.
Guidance. Those torch
cuts inventoried will be “grandfathered in” and any torch cuts found after
the expiration of one year that are not inventoried must be slow ordered to
Class 2 speed and removed within 30 days of discovery. If a railroad chooses to
upgrade a segment of track to Class 3, and passenger trains are operated, all
torch cuts must be removed before speeds can exceed the maximum for Class 2
track. If a railroad chooses to upgrade a segment of track from any lower class
to Class 4 or 5, it must remove all torch cuts.
123(a) In Classes 3 through 5 track, where timber crossties are
in use, there must be tie plates under the running rails on at least 8 of any 10
consecutive ties.
123(b) In Classes 3 through 5 track no metal object which causes
a concentrated load by solely supporting a rail shall be allowed between the
base of the rail and the bearing surface of the tie plate. This paragraph (b) is
applicable September 21, 1999.
Guidance. Inspectors
should consider this section jointly with the requirements for crossties and
rail fastenings and report tie plate conditions as defects where safety is
impaired by the absence of tie plates.
In Classes 3 through 5 track no metal object that causes a
concentrated load by solely supporting a rail shall be allowed between the base
of rail and the bearing surface of the tie plate. The specific reference to “metal
object” is intended to include only those items of track material that pose
the greatest potential for broken base rails such as track spikes, rail anchors,
and shoulders of tie plates. The phrase “causes a concentrated load by solely
supporting a rail” further clarifies the intent of the regulation to apply
only in those instances where there is clear physical evidence that the metal
object is placing substantial load on the rail base, as indicated by a lack of
loading on adjacent ties.
(a) Track shall be fastened by a system of
components that effectively maintains gage within the limits prescribed in §
213.53(b). Each component of each such system shall be evaluated to determine
whether gage is effectively being maintained.
Guidance: "Rail
fastening systems" include modern-day elastic fastening systems, which can
consist of abrasion pads, insulator clips, shoulder inserts cast into concrete
ties, as well as the fastener itself, of which many different designs are in use
today. The fastening system can also be of the traditional cut spike variety,
with or without tie plates. The failure of certain critical components within a
particular system could adversely affect the ability of the individual fastener
to provide adequate gage restraint. The wording of this regulation provides for
an evaluation of all components within the system, if necessary, when
degradation of the fastening system has resulted in problems maintaining gage
within the limits prescribed in § 213.53(b).
When an inspector identifies a gage geometry condition where the fastener
system has degraded and the location in question meets the factors described
below, the inspector must examine each component of the fastener system (e.g.,
clip, insulating pad, bolts, spiking pattern, etc.). The inspector should
describe the nature of the failed components on the F6180.96 form. If a fastener
condition causes the gage to exceed the limits of § 213.53, the inspector shall
report the condition as a gage defect and describe the nature of the fastener
condition on the same defect line of the report.
This section requires the inspector to exercise judgment in evaluating the
condition of fasteners. The following factors should be considered in the
evaluation:
• Gage exceeding the limits of § 213.53 (in such cases gage and track
class will govern).
• Gage
close to the limits of § 213.53 with evidence of recent widening.
• Evidence of recent rapid deterioration of gage with probable continued
deterioration.
• Evidence of recent significant damage to rail fasteners to the extent
that gage widening is probable.
• Evidence of recent maintenance work improperly performed resulting in
lack of sufficient fasteners to prevent gage widening under expected traffic.
• Traffic conditions, including speed, tonnage, and type of equipment.
• Conditions of curvature and grades.
FRA inspectors may use a PTLF described in § 213.110 for the purposes of
measuring the effectiveness of fasteners. Refer to Appendix D - PTLF
instructions for non-GRMS territory under § 213.53.
A unique attribute of concrete crossties is the abrasion that can occur
between the base of the rail and the rail-seat on the crosstie, a component of
the rail fastening system. A variety of tie pad designs and materials are placed
between the rail and the ties to mitigate abrasion. However, unequal or
"wedged" abrasion of the rail seat can be problematic for a high-speed
or high-tonnage operating environment that may cause rail fasteners to become
loose under load or in extreme cases cause rail-tilt or rollout. See the
following figure. Accordingly, inspectors should look for rail rollout due to
rail seat abrasion on concrete crossties, particularly in territory with heavy
traffic levels and moderate curvature. The mechanics of this condition on
concrete crossties include the following elements:
• Concrete wear or abrasion
resulting in loose rail clips, insulators, and pads.
• Loose components allow more
moisture and abrasives to enter rail seat.
• Once the field side of the
rail base wears through the tie pad and contacts the concrete tie rail seat,
rapid cutting into the concrete (accelerated abrasion) can occur.
• Signs and symptoms of
concrete crosstie rail seat abrasion include.
• Tie pad crushed or squeezed
out (maintaining integrity of the tie pad is essential).
•
Insulators crushed, moving, or missing.
• Clips loose indicating loss
of pressure on the rail base (loss of toe load).
• Longitudinal rail movement.
• Indications of cement colored
paste in the ballast from the abraded rail seat.
• Metal flaking or grease
streaks in the center of the low rail in a curve caused by the outer rim of
wheel (or false flange) placing excessive pressure on the head of the rail, a
condition generally created by gage-widening.
Based on the above discussion, it
is apparent that rail-seat abrasion on concrete ties causes rail rollout. As
rail rollout occurs, it decreases the effectiveness of the rail fasteners and
will often lead to gage geometry conditions. As a general rule, inspectors
should cite this condition as a rail fastener defect (213 defect code 0127A).
However, where rail rollout causes the gage to exceed the threshold for the
designated class of track, inspectors should cite this condition as a gage
defect (see § 213.53).
Rail anchors are not considered
to be a rail fastener. In areas where rail anchors are used in combination with
resilient fasteners on concrete ties, the resilient rail fasteners that normally
perform a dual function to restrain rail laterally and longitudinally should
only be evaluated on their ability to provide lateral restraint to prevent
gage-widening in regard to this section.
An insufficient fastener defect
should be written when an unsafe condition results from missing or defective
fasteners (e.g., heads of cut spikes sheared off at throat) on otherwise
supportive crossties.
(b) If rail anchors are applied to concrete crossties, the combination of the
crossties, fasteners, and rail anchors must provide effective longitudinal
restraint.
Guidance: This
paragraph requires that if rail anchors are applied to concrete crossties, then
the combination of the crossties, fasteners, and rail anchors must provide
effective longitudinal restraint. "Effective longitudinal restraint"
is a performance-based standard.
(c) Where fastener
placement impedes insulated joints from performing as intended, the fastener may
be modified or removed, provided that the crosstie supports the rail.
Guidance: addresses
instances where fastener placement impedes insulated joints from performing as
intended by permitting the fastener to be modified or removed, provided that the
crosstie supports the rail. "Support" means that the crosstie is in
direct contact with the rail or leaves an incidental space between the tie and
rail. Certain joint configurations do not permit conventional fasteners to fit
properly. As a result, manufacturers offer a modified fastener to fit along the
rail so that the fastener provides the longitudinal requirement, or it is
removed completely, providing lateral restraint is accomplished by ensuring full
contact with the rail or additional placement of anchors on the base of the
rail.
Additionally, FRA notes that the requirement of having an
effective crosstie within a prescribed distance of a joint contained in §
213.109(e) would apply, without modification for insulated joints. FRA has not
mandated what type of equipment or what manufacturer a track owner must use, but
instead has determined to regulate the performance of the material to the
minimum safety standards promulgated in Part 213.
133(a) In turnouts and track crossings, the fastenings must be
intact and maintained so as to keep the components securely in place. Also, each
switch, frog, and guardrail must be kept free of obstructions that may interfere
with the passage of wheels.
Guidance. There are
several types of fastenings, which include reinforcing straps, connecting rods,
rail hold down clips, and braces. (For a more extensive compilation of
fastenings, see the fasteners listed in defect codes 213.133. Where fastenings
are loose or missing, inspectors should cite the railroad using 213 defect code
0133A15 (Turnout or track crossing fastenings not intact or maintained.) In
addition, where fasteners are loose or missing and there is an apparent
contributing condition (e.g., a large section of the casting is broken out at an
at-grade rail to rail crossing), inspectors should include a description of that
contributing condition in their inspection report.
133(b) Classes 3 through 5 track shall be equipped with rail
anchoring through and on each side of track crossings and turnouts, to restrain
rail movement affecting the position of switch points and frogs. For Class 3
track, this paragraph (b) is effective September 21, 1999.
133(c) Each flangeway at turnouts and track crossings must be at
least 1½ inches wide.
Guidance. A turnout is a
track arrangement consisting of a switch and frog extending from the point of
the switch to the heel of the frog. This arrangement allows engines and cars to
pass from one track to another. Because of the operating or movable parts and
lateral thrust, it is essential that fastenings be in place, tight, and in sound
condition.
A track crossing (diamond) is an assembly used where two tracks
intersect at grade permitting traffic on either track to cross the rails of the
other. It may consist of four frogs connected by short rails, or a plant
manufactured “diamond.” Because of the impact a crossing is subjected to, it
is essential that fastenings be in place, tight, and in sound condition. Each
switch, frog, and guardrail must be kept free of obstruction.
Anchors on each side of a turnout or crossing and through a
turnout are required on Classes 4 through 5 track. For Class 3 track, this
requirement is effective on September 21, 1999. In determining the adequacy of
anchors at and on each side of a turnout or crossing and through turnouts,
inspectors should determine the capability of these devices to:
• Restrain rail.
• Assure proper fit of
switch points.
• Prevent line
irregularities.
Ties and timbers at switches and crossings must be of sound
condition, well-tamped, and the roadbed must be adequately drained.
Flangeways at turnouts and track crossings must be at least 1½
inches wide.
Turnouts and track crossings must be walked and measurements
made before they can be included on the F6180.96 form as a unit inspected.
135(a) Each stock rail must be securely seated in switch plates,
but care shall be used to avoid canting the rail by overtightening the rail
braces.
Guidance. The TSS under
§ 213.135 specifies the requirements for switch restraint, movement, and fit.
Each stock rail must be securely seated in the switch plates. Various
conditions, such as loose braces or hanging ties, can cause a stock rail to
become unseated. In these situations, inspectors should cite the railroad with
213 defect code 0135A1. Alternatively, a stock rail can become unseated if the
braces are overtightened during maintenance. In these situations, inspectors
should cite the railroad with 213 defect code 0135A2.
135(b)
Each switch point shall fit its stock rail properly, with
the switch stand in either of its closed positions to allow wheels to pass the
switch point. Lateral and vertical movement of a stock rail in the switch plates
or of a switch plate in a tie shall not adversely affect the fit of the switch
point to the stock rail. Broken or cracked switch point rails will be subject to
the requirements of §213.113, except that where remedial actions C, D, or E
require the use of joint bars, and joint bars cannot be placed due to the
physical configuration of the switch, remedial action B will govern, taking into
account any added safety provided by the presence of reinforcing bars on the
switch points.
Guidance. This paragraph
recognizes the existence of reinforcing bars or straps on switch points where
joint bars cannot be applied to certain rail defects, as required under § 213.113(a)(2), because of the physical configuration of the switch. In these
instances, remedial action B will govern, and a person designated under § 213.7(a), who has at least 1 year of supervisory experience in track
maintenance, will limit train speed to that not exceeding 30 mph or the maximum
allowable under § 213.9(a) for the appropriate class of track, whichever is
lower. Of course, the person may exercise the options under § 213.5(a) when
appropriate.
Section 213.135(b) addresses cracks in the switch rail (point)
with reinforcing straps acting as surrogate joint bars. If the switch point rail
is not cracked, and only the straps are cracked, then it is not appropriate to cite §
213.135(b); and inspectors
should cite the appropriate defects under § 213.133(a). Normally, minor cracks
in a strap are not a major concern. However, if a strap is fully broken and
causing other problems (e.g., loose switch clip, etc.), then § 213.133
(Turnouts and track crossing generally) would be appropriate. If the straps and
switch point rail are both broken, then there is an unprotected rail break and
inspectors should cite the appropriate defect under § 213.113.
Most industry standards call for a 4¾-inch opening between the
switch point and the stock rail, measured at the No. 1 switch rod. As components
wear, “lost motion” will result. When the problem of elongated switch clip
and/or rod holes is encountered, the switch rods may be adjusted at the clip
(e.g., adjustable side jaw clips, rocker clips, etc.). Adjustment may also be
accomplished at the switch stand depending on the design of the assembly. In
some cases, lost motion may be compensated by the addition of properly designed
shims between the switch clip assembly and the switch rail.
When the opening is substantially less than the standard
dimension, wheels can still pass through the switch as intended. However, the
backs of wheels may contact the inside rail head of the open switch rail. This
interaction can cause undesirable lateral pressure against the switch rail. This
pressure can contribute to broken heel block bolts, cause cracked or broken
switch clips, and broken switch crank cross pins. In extreme circumstances, the
closed point can open under movement because of the transfer of lateral loads
through the switch rods. In these circumstances, inspectors should make an extra
effort to determine the condition of all affected components. The amount of
throw is one of the many factors that must be taken into consideration when
determining the railroad’s compliance with § 213.133
and § 213.135.
Based on the above, make sure that switch points fit snugly
against the rail when the switch is thrown in either position. As appropriate,
request that the railroad representative operate the switch to test for lost
motion and/or loose connections.
The Appendix to the American Railway Engineering and Maintenance
of Way Association (AREMA) Portfolio of Trackwork Plans contains the following
split switch terms:
• “Split Switch with
Uniform Risers - A split switch in which the switch rails have a uniform
elevation on riser plates for the entire length of the switch, and therefore not
having a heel slope, the point rail rise being run off back of the switch in the
closure rails.”
• “Split Switch with
Graduated Risers - A split switch in which the switch rails are gradually
elevated by means of graduated riser plates until they reach the required height
above the stock rail, and therefore having a heel slope.”
The heel of the switch point is higher than the stock rail at
the heel joint with the uniform riser layout while, on the graduated layout, the
switch point is at the same elevation as the stock rail. The mixing of uniform
riser and graduated riser plates in the same switch, while not specifically
addressed in the TSS, can cause undesired stress in the switch rails and closure
rails. Inspectors should make a note of the intermixing of switch plates in
turnouts that have a high amount of traffic.
135(c) Each switch shall be maintained so that the outer edge of
the wheel tread cannot contact the gage side of the stock rail.
Guidance: :
Inspectors are to examine the seating of stock rails in the switch plates to
ensure that the outer tread of a wheel cannot engage the gage side of these
rails. Grease lines or slight groves running at a slight angle on the tread of a
stock rail can provide inspectors with clues about the wheel/rail interface.
These marks can be found in the area where wheel treads transition from the
switch rail to the stock rail. When found, inspectors should closely examine the
gage side of the stock rail to make sure the outer edge of wheel treads are not
contacting the gage side of the stock rail. As shown in the following figure,
this type of defect can occur when a worn switch rail and switch plates remain
in place after a stock rail has been renewed. This causes the switch rail to
drop down from the same level as its corresponding stock rail. The danger
associated with this condition is the possibility that the outer edge of a wheel
can contact the gage side of the stock rail during a trailing movement through a
switch, thereby turning over the stock rail.
Other items that can cause outer
edge wheel contact include improper surface, poor crosstie condition, loose rail
braces, stock rails not securely seated, switches where the majority of the
traffic uses one side of the turnout, and insecure jointed heel blocks with
improper elevation.
135(d) The heel of each switch rail shall be secure and the
bolts in each heel shall be kept tight.
Guidance. At least two
tight bolts in each rail are required to ensure that the heel of each switch
rail is “secure” for purposes of determining compliance with § 213.135(d).
Examine the heel block, its fastenings, and bars; or, in the absence of a heel
block, (which is known as a floating heel block) examine that assembly.
If heel joints were considered to be a normal joint, only one
bolt per rail end would be required in the heel for Class 1 track. However, the
heel joint functions in a different manner than a normal track joint. The heel
joint serves as the pivotal point for the rotation of the switch point. It helps
maintain the proper horizontal, vertical, and longitudinal fit of the switch
point against its stock rail. One bolt per rail end in Class 1 track at the heel
joint does not provide redundancy. The loss of the single bolt in the rail end
at the heel joint could have serious safety consequences.
Some railroad heel joints have as many as six bolts for the
higher track classes. Typically, when railroads plan to field weld, they do not
drill the middle two bolt holes in the rail of a six-hole joint bar. This
practice, which provides for at least two bolts in each rail end of the heel,
satisfactorily secures the assembly.
The switch heel assembly with joint bars also performs the
function of a joint. As such, where there is an improper joint bar at a heel
block, an inspector should cite § 213.121 (Rail joints). One example of an
improper joint bar is the installation of a six-hole joint bar where a five-hole
bar, by design, should be used. This would be a deviation of § 213.121, because
it is an improperly designed bar for that application, which may make it
difficult to throw the switch or may cause gapping.
135(e) Each switch stand and connecting rod shall be securely
fastened and operable without excessive lost motion.
Guidance. For
hand-operated switch stands of virtually all types, rotary motion imparted to
the vertical spindle within the stand by the person operating the hand lever is
translated into (practically) linear movement of the connecting rod by the right
angle combination of the end of the spindle beneath the stand and its attached
crank. Unless cranks are integrated with the spindle by casting during
manufacture, they are separate pieces that must be joined. Cranks are attached
to spindles in one of two ways: (1) they may be turned into a threaded opening
in the side of the spindle or (2) the crank may be fabricated to have a square
or rectangular smooth opening at one end, which can be moved from below, up onto
a spindle having a similar cross-section to a position where it can be secured
in place by a horizontally inserted cross pin that simultaneously engages the
crank with the spindle. For ease of reference in this discussion, the first case
will be referred to as Type A and the second case as Type B. An undesired
decoupling of the connecting rod and the switch stand can occur in Type A if the
bolt attaching a connecting rod to a threaded crank comes out and, in Type B,
separation of the crank and the spindle can occur in the absence of the cross
pin. Either instance could result in the gapping of the closed switch point
under train movement, unless some other device is in place to physically
restrain the points.
Type B switch stands may at times have a plate-like arrangement
of sheet metal suspended from the headblock timbers beneath the assembly. This
device, generally a shallow “U” shape, is commonly referred to as a “safety
plate.” The function of the plate is twofold: (1) to restrict the downward
movement of the crank on the spindle, should the cross pin be absent, so the
crank does not completely separate from the spindle, and (2) to keep a
vertically unrestrained crank from sliding down the spindle far enough to permit
the connecting rod enough space below the bottom of the switch stand to move up
off the lug of the crank. There have been cases where cross pins have fractured.
The plate itself is deformed so that the downward displacement of the crank was
sufficient to enable the connecting rod to clear the crank lug without
contacting the base of the stand. This leads to decoupling of the switch stand
and the connecting rod.
Inspectors must constantly bear in mind those aspects of switch
stand performance that are crucial to functional safety. This discussion
concentrates on that region of the mechanical linkage between the switch points
and the switch stand that may be difficult to observe in the course of a turnout
inspection.
There are several different styles of Type B switch stands that
are in use on main tracks and yards in the railroad industry. These models
differ in minor ways. Nevertheless, they rely on the cross pin restraint of the
spindle/crank subassembly and they all share vulnerability to the uncoupling of
the switch stand and connecting rod. A turnout inspection must include
examination of these hard to see parts even.
Inspectors should examine the
effectiveness of the fastening system of the switch stand to the head block ties
and look for signs of movement of the switch stand which can result in loss
motion leading to a gapped switch point.
135(f) Each throw lever shall be maintained so that it cannot be
operated with the lock or keeper in place.
Guidance. Inspectors must
examine each switch lock and keeper. Certain types of switch stands “internally
toggle” when the handle is thrown all the way in either position to hold the
switch point against its stock rail. These types of switch stands are used in
other than main track and often are a “semi-automatic” design whereby a
train trailing the turnout, with the switch in the incorrect position, will
initially force the points over. The final throw is completed by the internal toggling action of the switch stand. By design
and application preference, these switch stands might not have a lock or keeper
for other than main track applications (see the following figure).
There is a concern associated with this type of switch stand
retrofitted with an “S”-shaped strap, bolted and welded to one of the two
flanges of the throw lever stop. The bolt has been proven to be ineffective in
preventing rotation of the strap, and the bead weld, placed by the manufacturer
at the top of the strap, cracks from repeated depression of the keeper. The
strap rotates downward, altering the location of the lock shackle or keeper,
allowing the throw of the switch lever without removal of the lock or keeper.
If the above types of switch stands are used at switches and
derails not requiring securing, the soundness of the strap is not in question.
However, if the track owner requires that the stand be secured by lock or
keeper, a weld displaying cracks will call into question the soundness of the
latch mechanism and 213 defect code 0135F, throw
lever (potentially) operable with
switch-lock or keeper in place, should be cited without recommending a
violation. If the track owner fails to aggressively address and correct the
potential defect on the subject types of switch stands, consider recommending a
violation to Chief Counsel.
49 CFR 218.105(b) requires
that all hand operated main track switches are to be locked. An ineffective or
worn latch or hasp can allow the throw lever of the switch to be operated with
the lock in place. There are several different types and models of hand operated
switches in use; Inspectors should inspect each latching mechanism to for wear
and possible operation of the throw lever with the lock in place. The inspection
should include stepping on the latch and observation of the clearance between
the throw lever and the opening created when the latch is depressed with lock in
place. Inspectors should not attempt to raise the operating lever and request
the accompanying railroad representative to lift the handle if its operation
through the latch appear probable, and it is safe to do so. As shown in figure
below, the throw lever is clearly operable with the lock in place.
Many power switches are
operable by either power (remotely by control operator or train dispatcher) or
by hand, frequently called dual control switches. Inspection of this type of
switch machine is similar to the typical hand operated switch stand. Most have
two levers, one to remove the switch machine from power operation, and one that
acts as the throw lever.
The latches should be inspected for the possibility of the power lever or throw
lever being operated with the lock in place. (See the following two figures)
135(g) Each switch position indicator shall be clearly visible
at all times.
Guidance. Examine
condition of switch position indicator and note any unnecessary obstruction to
its visibility. This requirement does not mandate that every switch have a
position indicator but merely requires such devices to be clearly visible when
installed on a switch stand.
135(h) Unusually chipped or worn switch points shall be repaired
or replaced. Metal flow shall be removed to insure proper closure.
Guidance. The rule does
not provide for specific dimensions for determining when switch points are “unusually
chipped or worn.” The accident/incident database indicates that worn or broken
switch points are the largest single cause of derailments within the general
category of “Frogs, Switches, and Appliances.” However, most of these
derailments are related also to other causal factors such as wheel flange
condition, truck stiffness, and train-handling characteristics. Therefore,
qualified individuals must use their experience to determine when switch points
are “unusually chipped or worn.”
135(i) Tongue & Plain Mate switches, which by design exceed
Class 1 and excepted track maximum gage limits, are permitted in Class 1 and
excepted track.
Guidance. This paragraph
provides an exemption for this item of specialized track work, primarily used in
pavement or street railroads, which, by design, does not conform to the maximum
gage limits prescribed for Class 1 and excepted track. This type of special work
is fabricated from “girder rail,” which includes a tram (flangeway) rolled
into the rail section. A “mate” is similar to a frog but located on the side
of the switch that is equivalent to a straight stock rail. The switch, when in the open or curved position,
guides wheels past the mate on the turnout (curved) side in a manner similar to
a frog guardrail.
Guidance, General. In
addition to considering the above criteria, inspectors must perform the
following when inspecting switches:
• Check alinement, gage,
and surface.
• Examine condition as to
the wear of switch points and stock rails.
• See that all bolts, nuts,
cotter pins, and other fastenings are in place, in good condition, and are
properly tightened;
• See that switch points
fit snugly against the rail when the switch is thrown in either position.
Request that the railroad representative operate switches to test for lost
motion and/or loose connections.
• If applicable, examine
the rod and fastenings that connect the switch point to the switch circuit
controller to ensure they are in place and in good condition.
• Examine the condition and
support of spring and power-switch machines and hand-thrown switch stands,
including automatic or safety switch stands. Switch stand and machine fastenings
to the head block ties must be tight to avoid any movement or play.
• Examine switch-lock and
keeper.
• Examine condition of
switch position indicator and note any unnecessary obstruction to its
visibility.
• Examine the heel block,
its fastenings, and bars; or, in the absence of a heel block, examine the
floating heel of the switch point.
• Examine the seating of
stock rails in the switch plates to ensure that the outer tread of a wheel
cannot engage the gage side of these rails and that chairs or braces do not cant
these rails in. This defect is particularly a problem for travel in the
direction from the frog to the switch (trailing movement). Grease lines or
slight groves running at a slight angle on the tread of a stock rail can provide
inspectors with clues about the wheel/rail interface. These marks can be found
in the area where the wheel tread transitions from the switch rail to the stock
rail. When found, inspectors should closely examine the gage side of the stock
rail to make sure the outer edge of wheel treads are not contacting the gage
side of the stock rail.
137(a) The flangeway depth measured from a plane across the
wheel-bearing area of a frog on Class 1 track may not be less than 1⅜ inches, or less than 1½ inches on Classes
2 through 5 track.
Guidance. The Association
of American Railroads (AAR) Field Manual of Interchange Rules states that a
wheel is condemnable when the flange height is “1½ inches or more above the
approximate center line of the tread.” The AREMA Portfolio of Trackwork Plans,
Point and Flangeway Dimensions, provides a designed flangeway depth of at least
1¾ inches. Therefore, the amount of clearance between a worn wheel with a high
flange and the bottom of a new frog’s flangeway may be as little as three-eighths
inch. At higher speeds, if a worn frog has a flangeway less than 1½ inches, the
wheel flange could “bottom out” in the flangeway and result in severe damage
to the frog.
Section 213.137(a) permits a flangeway depth of 1⅜
inches in Class 1 track. In such a condition,
a wheel that is approaching condemning limits might contact the bottom of the
flangeway. As such, it is possible to have evidence of wheel flangeway contact
on the bottom of the flangeway caused by noncompliant wheels.
137(b) If a frog point is chipped, broken, or worn more than
⅝ inch down and six inches back, operating
speed over that frog may not be more than 10 m.p.h.
Guidance. If a frog point
is chipped, broken, or worn more than five-eighths inches down and 6 inches
back, a collapse of the point area is possible after repeated wheel impacts.
This parameter requires a defect to be more than five-eighths inches down from
the original profile to a location 6 inches back toward the heel to be
considered. For example, a frog point that is seven-eighths inches below its
original profile at the actual frog point and seven-eighths inches below at a
position 6 inches back toward the heel of the frog would be a defect.
For a severe condition that would not meet this criteria such as
a breakout at a frog point that is only 4 inches in length and greater than
five-eighths inches down, inspectors may consider using the 213 defect code
0137E.
While this condition may not be a defect, it is a method to
notify a railroad of a condition that the inspector feels the structural
integrity of the frog is in question. Please note that 213 defect code 0137E
does not link to a paragraph in the TSS and may only be used as an advisory to
the railroad.
Another possible result of a severely worn frog point,
especially when coupled with a worn or loose guardrail, is that a railroad wheel
may “hit” the point and climb to the wrong side of the frog. Also see Figure
27 for information about “depressed point” designs that may influence the
measurement of a worn or broken frog point.
137(c) If
the tread portion of a frog casting is worn down more than ⅜ inch below
the original contour, operating speed over
that frog may not be more than 10 m.p.h.
The tread of the frog is considered to be any portion that is contacted by
the tread of the wheel except for portion of the frog from the actual point to a
position 6 inches back towards the heel [this area is addressed by §
213.137(b)]. As shown in the following figure, the measurements of the portion
of the tread further back than the 6 inch position may be taken by placing a
straightedge positioned transversely. The following figure shows a rail bound
manganese frog design with an actual frog point that is three-sixteenths inch
lower than the tread portion. A frog built without manganese insert (e.g., a
frog composed of Tee rails called a bolted rigid frog) will have a point with a
similar profile. Called a depressed point, the tread will taper up to the top of
the rail profile in the direction toward the frog heel in varying distances
depending upon the different manufacturing designs and size of frogs, but not
less than 5 inches.
An alternate rail bound manganese
or solid cast frog design includes a profile whereby the tread portion of the
casting adjacent to a frog point is manufactured to a plane one-eighth inch
above the top of the rail profile (wing wheel riser). See following figure.
These design characteristics need to be considered when measuring tread wear as
discussed below.
When measuring tread wear, the distance from the bottom of the straight edge
to the worn tread at the riser is measured. Various types of gauges, such as a
folding leaf gauge with different degrees of taper, or a wedge-type gauge, may
obtain this measurement. Tape measures are also frequently used to measure tread
wear.
There is a wide variety of new frog designs being developed and used in the
industry that may require different measuring techiques or tools and must be
given consideration; one example is the conformal frog. The design of the
conformal frog casting through the original tread and point area is tapered to
the same angle (1:20 ratio) as the tread of the wheel to reduce impact load and
smooth wheel transition. The wing or transition portion of the casting of a
conformal frog is raised and extends above the wrap or wing rail of the frog.
Measuring the amount of wear on a conformal requires use of a special
"straight edge" to properly measure tread, point, and flangeway depth
due to the "conformal" design. Use of a standard straight edge on a
conformal frog may result in improper wear limit measurement.
If the tread is worn more than three-eighths of an inch, the corresponding
flangeway depth may also be reaching critical limits. Since the manganese insert
is typically designed to be about 2 inches thick at the wall of the flangeway
and about 1⅜ inches or less at the bottom of the flangeway, wear in this
condemning range could result in structural failure of the frog.
Frogs frequently exhibit small spalling (pitting) in the tread. Usually, this
type of spalling is not hazardous. Measurements of tread wear should be made
over a length that is worn down due to abrasion or plastic flow of metal not at
the bottom of small spalls. However, if the depression is of sufficient size to
permit the tread of a wheel to follow that depression, tread wear should be
measured at the depression.
To measure flangeway depth, place a straight edge across the frog at the area
of concern. Measure the space between the underside of the straight edge to the
bottom of the flangeway and the space between the underside of the straight edge
and the tread. As shown in the following figure, subtract the tread value from
the flangeway value to obtain the actual flangeway depth.
When a railroad wheel approaches
the frog in the facing direction, the weight of the wheel is supported on the
tread of the frog opposite the point until the wheel reaches the transition
point, about 6 inches back from the actual point. At this location, the weight
is transferred to the frog point.
137(d)
Where frogs are designed as flange-bearing, flangeway
depth may be less than that shown for Class 1 if operated at Class 1 speeds.
Guidance. This paragraph
provides an exemption for an item of specialized track work that by design does
not conform to the minimum flangeway depth requirements prescribed in paragraph
(a) of this section. Called a flange-bearing frog, this technology is under
consideration as a method of reducing impact loads at frogs. This design is a
new concept for track above yard speeds but has been used extensively in light
rail transit trackwork.
There are a number of frog designs in use throughout the
industry and the most common types are rail bound manganese and bolted rigid
(stiff). The special attributes of spring frogs are covered under § 213.139.
Conventional moveable point frogs are found at flat angle track crossings and
slip switches (Figure 30). This type of movable point frog is similar to a
switch because of its movable points that fit against a knuckle rail, which is
like a stock rail.
In recent decades, new technology movable frogs have been
introduced in the Nation and there are two types—“swing nose” (Figure 31)
and movable wing (Figure 32). Conventional movable point frogs and swing nose
frogs are virtual switches; therefore there are no guardrails. As such, it is
appropriate to use the applicable elements of § 213.135 (Switches) in an
inspection report when encountering defects in these movable point frogs. For
example, a movable point that does not fit its knuckle rail properly would be
covered under § 213.135(b) (each switch point shall fit its stock rail
properly).
The movable wing rail type frog is similar to a spring frog but
both wing rails are moved remotely in synchronization with the switch points. It
is appropriate to use the applicable elements of § 213.139
(Spring rail frogs)
in an inspection report when encountering defects. Like above, when using any of
the 139 series defect codes it is necessary to include 213 defect code 0133A15
– Turnout or track crossing fastenings not intact or maintained.
The following are the key elements to consider when inspecting
new technology frogs:
• Bolting or fastener
designs that fasten the movable point frog to concrete or timber switch ties are
considered fasteners in the same manner as cut spikes. Fastenings are discussed
under § 213.127 of this manual. Bolts that connect movable frog components
together are considered frog bolts and must be addressed by using 213 defect
code 0133A12, Loose or missing frog bolts.
• Of paramount importance
is a proper fit of the vee point rails against the wing rails on movable frogs.
Inspectors must use their judgment to determine if the point fits the wing rail
properly to allow wheels to pass the frog point. Movements of the wing rail must
not adversely affect the fit of the frog point to the wing rail. When an
inspector encounters a condition on a movable frog which should be addressed on
the inspection report and no existing code is available for that condition, 213
defect code 0137E will be acceptable with a full description of the condition in
the inspection report.
• Unlike rail bound
manganese frogs, the running surface of most, if not all, movable frogs are made
of hardened rail. Inspectors must be aware that this rail may contain defects
that require remedial action under § 213.113. Asymmetrical rails found in some
switch points and frogs must be closely examined during inspections, as this
appears to be a potential weak spot where a crack or break could occur.
• When performing
inspections, FRA inspectors should discuss any concerns about an advanced
turnout with appropriate railroad personnel. Inspectors should consult with the
regional track specialist to resolve any questions about the safety of these
installations.
General Guidance:. The
various types of frogs available for specific applications include bolted rigid,
solid manganese, self-guarded, railbound manganese, spring rail, movable point,
cast, or swing nose. On railbound manganese frogs, the normal wear pattern is in
the manganese insert.
An inspector, in addition to measurements described in the TSS,
should see that a frog is supported throughout on well tamped and sound ties.
The requirements for flangeway depth in paragraph (a) and the
requirements for tread wear in paragraph (c) also apply to crossing frogs. Since
the designed flangeway depth is also 1⅞ inches,
the safety concerns are the same, as excessive wear on the tread portion could
result in a wheel flange striking the bottom of the flangeway and causing
structural damage to the frog.
Inspectors must evaluate cracks or breaks in frog castings or
rail defects in the non-running portion of wing rails in terms of their
potential effect on the safe passage of rolling stock. In particular, when
making the evaluation:
• The inspector should
determine if there is a loss or imminent loss of wheel guidance due to a loss of
functional integrity.
• The inspector should not
consider cracks or breaks in a manganese frog casting that do not affect the
safe passage of rolling stock to be a defective condition. If a severe crack, or
a series of cracks, creates a condition where the breaking out of a piece of the
casting is imminent, the use of 213 defect code 0137E should be considered.
Cracks or wear that develop into a loss of functional integrity should be
addressed by using 213 defect code 0137B or 0137C, which govern worn frog points
and castings.
• Rail defects in the
non-running portion of wing rails should be addressed by using 213 defect code
0137E.
139(a) The outer edge of a wheel tread shall not contact the
gage side of a spring wing rail.
Guidance: :
Inspectors must closely examine every spring rail frog encountered during an
inspection. While spring rail frogs have been successfully used for many years,
their unique design requires special maintenance attention to avoid derailment
hazards to trailing point train movements on the main track. If a spring wing
rail is higher than the top running surface of frog at the transition area, a
wheel during a trailing move may push the spring wing rail open causing rail
roll out or wide gage. Hollow or false flange wheels are more prone to cause
this occurrence.
A beginning sign of outer edge wheel tread contact will appear as gouging on
the gage corner of the wing rail behind the point of frog at the transition
point similar to the stock rail/switch point configuration. While some spring
frogs have a "relief" groove built into the frog for this purpose,
inspectors must be acutely aware of any signs of the gage side of a spring wing
rail being struck by the outer edge of wheel treads. Wheel gouging must not be
confused with channeling in the spring wing rail that is incorporated at the
time of manufacture to accommodate wheel tread transition. Vertical deflection
at the toe of frog (213.139(b)) and hold-down housing clearance (213.139(e))
must be assessed when gage face wheel contact is observed. If the toe is not
solidly tamped and excessive horn and housing clearance exists, the wing rail
may have vertical motion while wheels are operating on the point rail in a
trailing-point movement and the forces on the wing rail will cause the wing rail
to move laterally, allowing the wheel to drop in at the throat of the frog.
139(b)
The toe of each wing rail shall be solidly tamped and
fully and tightly bolted.
Guidance: The
toe of each spring rail frog must be solidly supported, and proper hold-down
housing clearance must be maintained to avoid excessive vertical movement of the
wing rail. The combination of these two conditions can cause outer edge wheel
tread contact. The first sign that this is occurring will be gouging on the gage
corner of the wing rail behind the point of frog. Wheel gouging must not be
confused with channeling in the spring wing rail that is incorporated at the
time of manufacture to accommodate wheel tread transition.
If the toe is not solidly tamped and excessive horn and housing clearance
exists, the wing rail may have vertical motion operating on the point rail in a
trailing-point movement and the forces on the wing rail will cause the wing rail
to move laterally, allowing the wheel to drop in at the throat of the frog.
139(c) Each frog with a bolt hole defect or head-web separation
shall be replaced.
Guidance. Any bolt hole
defect or head-web separation in a spring frog of any dimension constitutes a
defect. This paragraph does not prescribe a corrective action other than “replacement.”
139(d) Each spring shall have compression sufficient to hold the
wing rail against the point rail.
Guidance: The
intent of the regulation is to ensure the spring holds the wing rail against the
point rail. Typically, if a wing rail is up against the point, it is an
indication that the spring is holding it as intended. If an inspector finds the
wing is not against the point he/she should determine the root cause of the
condition. A component such as loose bolt may be obstructing the closure and
213.133A12 should be cited. Without proper anchorage, the horn may bind in the
hold-down housing and defect 213.133B should be cited in classes 3-5. If there
is a suspicion that there is insufficient compression in the spring, the
railroad representative should determine its compliance.
139(e) The clearance between the hold-down housing and the horn
shall not be more than ¼ inch.
Guidance. Since the
spring wing rail is a movable part of a spring frog, it cannot be fastened down.
The hold-down housing and a horn assembly prevents the wing rail from moving up
higher than the top of the frog point. Figure 34 illustrates the proper method
to determine if there is excessive space between the hold-down housing and the
horn.
General
Guidance: Due to the
unique design characteristics of spring frogs, turnouts with this type of
appliance require special consideration in regard to guardrails. On the main
track side of a turnout, when trains are not "springing" the frog (by
design) and operating on an unbroken path, an extra length guardrail assures a
proper path for wheelsets.
A guardrail should be of sufficient length to cover the designed hinge
length. This keeps wheels off the spring wing rail from the point where this
rail is "hinged" through the frog throat and finally to the actual
frog point.
While the TSS does not address this design concept, inspectors should be
aware of this attribute of spring frogs. If a guardrail is of insufficient
length to cover the designed hinge length, any lateral wheel forces can cause
significant problems. Specifically, the guardrail and other frog elements will
quickly deteriorate, and in extreme circumstances, the wing rail can open while
trains are moving through the main track side which can result in an unprotected
wide gage. Inspectors should note on their inspection report any guardrail on a
spring frog that is not of the proper length or installed in the improper
position.
Another special consideration with regard to spring frogs is the longitudinal
relationship between the spring wing rail and frog point. If a turnout has
insufficient rail anchors to restrain longitudinal movement, the wing rail may
not function properly. Evidence that longitudinal movement is occurring may be a
gap between the wing rail and the frog point. Inspectors are reminded to refer
to § 213.133(b) that requires Classes 3 through 5 track to be equipped with
sufficient rail anchoring to restrict longitudinal rail movement. If
longitudinal movement is observed because of insufficient anchors on Classes 1
and 2 track, inspectors are encouraged to note this condition and inform the
railroad.
Spring frogs are manufactured with a steel base plate. Attached to the base
plate are clip plates, which are placed along the fixed side of the frog. The
clip plates, which are shaped into a right angle, are attached to the base plate
by bolts, welds, or both. Frog bolts are placed through the body of the frog and
through the vertical portion of the clip plates and tightened. This holds the
body of the frog to the clip plate assembly.
There are no gage holding fasteners along the movable side of the frog as
they would interfere with the spring wing rail. Therefore, it can be seen that
the frog bolts and clip plate assemblies, acting together, maintain alinement of
the spring frog. Care should be taken to ensure that the frog bolts and clip
plate bolts are in place and tight (213 defect code 0133A12). Also check clip
plates to see if welds are cracked or broken and check clip plates for cracks
and breaks at the corner where the plate bends from horizontal to vertical.
Where cracks or breaks in clip plates affect the fastening of the frog to the
base plate, use defect
213 code 0133A15 (insufficient fasteners).
In recent years, railroads have augmented the design of spring frog
installations by the application of improved stops to limit the amount of
movement of the spring rail. In addition, some frogs have been retrofitted with
welded stops. Most stops are designed to allow the wing to open no more than 1⅞
to 2¼ inches. When stops are properly installed, the risk of trailing point
derailments is reduced.
When spring frogs are equipped with the improved features, such as relief
grooves and stops, the inspector should evaluate the condition of the components
in order to ascertain that the improved features are functioning as intended.
When spring frog defects are found, the defective conditions must be repaired
as soon as possible. Combinations of the defects are especially hazardous. The
railroad must protect the movements over the frog with a speed restriction until
the defects are repaired.
Spring frog defects are considered as non-class-specific defects (see §
213.9); therefore, inspectors must consider the circumstances involved in
evaluating the remedial action taken by the railroad when spring frog defects
are found. Inspectors should consider all spring frog defects as serious defects
that must be repaired as soon as possible. In most circumstances, when it is
evident that the outer edge of the wheels are contacting the gage side of the
wing rail or a combination of spring frog defects exist, inspectors would expect
that the railroad would implement a speed restriction.
Some spring frogs are equipped with retarders that reduce the impact of the
wing on the point as the wing closes with each passing wheel in the diverging
route. The retarders may hang, causing the wing to remain open. Though the TSS
does not address this design concept, inspectors should still be aware of this
attribute of spring frogs because it could lead to further degradation of frog
components.
141(a) The raised guard on a self-guarded frog may not be worn
more than
⅜ of an inch.
Guidance. When examining
self-guarded frogs, observe the condition of the frog point, and where there is
evidence of wear caused by wheel flanges contacting the frog point, take
measurements to determine compliance with this section. To determine the amount
of wear on a raised guard, measure the thickness at a portion where there is
wear. Compare this measurement to a portion where there is no wear and the
difference between the two is equivalent to the amount of wear.
141(b) If repairs are made to a self-guarded frog without
removing it from service, the guarding face must be restored before rebuilding
the point.
Guidance. During repairs
of a self-guarded frog, it is imperative that the raised guarding face is
restored before the actual frog point. This precaution is necessary due to the
potential for a wheel flange striking the frog point.
Self-guarded frogs are designed for use in low speed track and
their use in tracks where speeds exceed 20 mph can result in excessive lateral
forces such as wheels “kicking” or in extreme cases wheels climbing up the
raised guard. The TSS does not prohibit the use of self-guarded frogs in any
class of track; however, inspectors are encouraged to inform a railroad of the
potential for problems that may occur if a self-guarded frog is found in a track
where speeds exceed 20 mph.
The guard check and guard face gages in frogs must be within the
limits prescribed in the following table:
Guidance. A guardrail is
installed parallel to the running rail opposite a frog to form a flangeway with
the rail and to hold wheels of equipment to the proper alinement when passing
through the frog.
A guardrail must be maintained in the proper relative position
to the frog in order to accomplish its critical intended safety function.
Inspectors should examine guardrails carefully to see that they are adequately
fastened, and when measuring guardrail gage, fully consider any movement of
guardrail or frog under traffic conditions.
This section clearly specifies allowable tolerances for guard
check and guard face gage for various classes of track.
When measuring guard check gage, it is important to consider the
path of wheels through the frog because the function of a guardrail is to keep
wheel flanges from striking the actual frog point. As reference, standard check
gage on a railroad wheel set is approximately 54½ inches (see Figure 36 for
approximate design check gage values). While the TSS minimum guard check gage is
less than wheel check gage in lower classes of track, the condition of the
actual frog point in relation to the path of wheels through a frog is a good
indicator of the effectiveness of a guardrail.
The critical area where guard check gage must be measured is at
the actual point of frog. Inspectors must also consider any unusual wear that
may exist at the actual frog point and position the track gauge or other
measuring device accordingly.
When measuring guard check gage,
dynamic lateral movement of the guardrail and/or frog shall be considered. In
the case of a frog that is moving laterally under train movement (floating), it
is important to consider the most restrictive measurement. Specifically, if
measuring guard check gage in a turnout where the frog can move toward the track
being measured due to train movement on the other track, that dynamic frog
position would be considered. See the figure below.
In severe cases, where a frog is severely floating (moving laterality under
load) and there is an accompanying condition (i.e., deteriorated crossties or
ineffective fasteners), FRA inspectors should cite the defect or recommend a
civil penalty for the accompanying condition (i.e., §§ 213.109 (Crossties) or
213.127 (Rail fastenings)).
Face gage is a dimension that becomes critical when the distance between two
opposing guardrails, or a guardrail and a frog wing rail, become larger than the
distance between the back of wheelsets. This would occur by improper
installation, or a condition such as a severe alinement defect. Normally,
face gage would be measured in the same vicinity as check gage. However,
inspectors should consider measuring face gage at other points in special
trackwork where there may be an indication that wheels are being
"pinched." For general reference, the following illustrates
approximate design face gage values.
Broken guardrails occur infrequently, since they do not support
the vertical wheel loads of passing trains. When evaluating a crack or break in
a guardrail, the inspector should be aware that cracks or breaks exist that do
not affect the ability of the guardrail to function as intended. If the
integrity of the guardrail is affected, the inspector will cite the defect using
213 defect code 0143A3, Cracked or broken guardrail.
There are many different types and designs of frog guardrail
designs. Some guardrail plates are recessed to seat the running rail, while
others are flat. Some guardrail plates are punched with spike-hole slots; others
are not. Other guardrails are bolted to the running rail. On some railroads, it
is normal practice not to spike the gage side of the running rail through the
guardrail area while some guardrail plates do not have holes punched for this
purpose. FRA has no record of serious safety problems that have developed
as a result of not spiking the running rail through the guardrail area.
If encountering a problem where the running rail has moved
laterally to create an unsafe condition, the inspector should use insufficient
fasteners defect code 213.127. Inspectors should discuss unique situations with
their regional track specialist.
While not a requirement of the TSS, guardrails have a straight
portion that guides wheels through the area from the “throat” to the actual
frog point. If inspectors find a guardrail where the straight portion does not
encompass this area, inspectors should bring this to the attention of the
railroad. Figure 39 illustrates the proper measurement points to determine
check/face gage compliance and shows the proper longitudinal relationship
between a guardrail and frog point.